Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Tasmeer Indigo Real Estate Development L.L.C تسمير اندجوللتطوير العقاري ش.ذ.م.م DLD developer no. 1739 · Registered with DLD on 28 September 2023 · Licence 1212769 2 projects in the DLD register: 0 completed, 1 under construction, 1 not started or pending. DLD projects register, export of 1 November 2026

Projects
2
in the DLD register
Completed
0
0 units delivered
Not yet completed
2
382 units in the pipeline

Delivery record

Projects: 2
Under construction 1Not started or pending 1
  • 0 units and villas in completed projects; 382 in projects not yet completed.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Tasmeer Indigo Real Estate Development L.L.C Most registered sales in the last 24 months first

Projects by Tasmeer Indigo Real Estate Development L.L.C
ProjectDLD status Built DLD end date Units Sales, 24 mo
SquareX Residence2919 · Al Barsha South Fourth · Jumeirah Village Circle Under construction 58% — 175 128
SquareX One3371 · Al Barsha South Fourth · Jumeirah Village Circle Not started 0% Jun 2028 19 mo to go 207 17

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 2, all pinned

SquareX Residence · 50–75% builtSquareX One · Not startedSquareX Residence · 50–75% builtSquareX One · Not startedMakani
50–75% built Not started

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.