DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

The Palm - Jumeirah CO. (L.L.C) شركة النخلة - جميرا (ش.ذ.م.م) DLD developer no. 103 · Registered with DLD on 10 January 2007 · Licence 543248 11 projects in the DLD register: 7 completed, 4 under construction, 0 not started or pending. 0 of the 4 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
11
in the DLD register
Completed
7
1,853 units delivered
Not yet completed
4
1,146 units in the pipeline
Past DLD end date
0 / 4
under construction with an end date

Delivery record

Projects: 11
Completed 7Under construction 4
  • Median time from start to completion: 20 months (6 completed projects).
  • 1,853 units and villas in completed projects; 1,146 in projects not yet completed.
  • Completed a month or more after their DLD end date: 1 of 7 completed projects with both dates. In 3 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
  • Under construction past their DLD end date: 0 of 4 projects with an end date.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by The Palm - Jumeirah CO. (L.L.C) Most registered sales in the last 24 months first

Projects by The Palm - Jumeirah CO. (L.L.C)
ProjectDLD status Built DLD end date / completion Units Sales, 24 mo
Marina Residence1297 · Palm Jumeirah Completed 100% Jun 2009 Completed 980 183
The Palm Tower1603 · Palm Jumeirah Completed 100% Nov 2021 Completed 442 85
Palm Beach Towers - 22429 · Palm Jumeirah Under construction 81.6% Dec 2026 1 mo to go 321 53
Palm Beach Towers -32449 · Palm Jumeirah Under construction 74.3% Dec 2026 1 mo to go 460 45
Palm Beach Towers -12406 · Palm Jumeirah Under construction 82.8% Dec 2026 1 mo to go 284 43
Palm Views - West1317 · Palm Jumeirah Completed 100% Nov 2014 Completed 104 40
Palm Views - East1316 · Palm Jumeirah Completed 100% Nov 2014 Completed 105 35
Como Residences2565 · Palm Jumeirah Under construction 24.8% Mar 2027 4 mo to go 81 25
Azure Residence1350 · Palm Jumeirah Completed 100% Dec 2015 Completed 179 23
Palma Residence1314 · Palm Jumeirah Completed 100% Feb 2015 Completed — 9
Club Vista Mare1351 · Palm Jumeirah Completed 100% Jun 2015 Completed 43 7

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 4, all pinned

3 projects3Como Residences · Under construction, 0–25% built3 projects3Como Residences · Under construction, 0–25% builtMakani
Under construction, 0–25% built 50–75% built 75–100% built Approximate location (ringed)

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.