Tiger Properties تايجر العقاريــــة 26 projects in the DLD register: 18 completed, 8 under construction, 0 not started or pending. 0 of the 5 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 26- Median time from start to completion: 40 months (18 completed projects).
- 6,921 units and villas in completed projects; 5,331 in projects not yet completed.
- Completed a month or more after their DLD end date: 6 of 18 completed projects with both dates. In 11 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 0 of 5 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Tiger Properties Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Red Square2789 · Al Barsha South Fifth · Jumeirah Village Triangle | Under construction | 26.7% | — | 835 | 596 |
| Auresta Tower3734 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 4.4% | Dec 2028 25 mo to go | 840 | 523 |
| Guzel Towers3458 · Al Barsha South Fifth · Jumeirah Village Triangle | Under construction | 7.3% | Dec 2027 13 mo to go | 522 | 407 |
| Neva Residences2544 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Mar 2026 Completed | 409 | 301 |
| Tiger Sky Tower2579 · Business Bay | Under construction | 10.2% | — | 849 | 296 |
| Ananda Residences3535 · Al Hebiah First · Motor City | Under construction | 3.2% | May 2028 18 mo to go | 1,027 | 278 |
| CLOUD Tower2212 · Al Barsha South Fifth · Jumeirah Village Triangle | Completed | 100% | Oct 2025 Completed | 456 | 258 |
| Seslia Tower2528 · Al Barsha South Fifth · Jumeirah Village Triangle | Completed | 100% | Jul 2026 Completed | 378 | 233 |
| Sky Gate Tower4120 · Al Barsha South Fifth · Jumeirah Village Triangle | Under construction | 4.7% | Feb 2028 15 mo to go | 431 | 220 |
| Jade Tower3074 · Wadi Al Safa 3 · Majan | Under construction | 11% | Mar 2027 4 mo to go | 436 | 202 |
| Nobles2208 · Business Bay | Completed | 100% | Aug 2024 Completed | 562 | 194 |
| Elbrus Tower2637 · Al Barsha South Fifth · Jumeirah Village Triangle | Completed | 100% | Sep 2026 Completed | 270 | 134 |
| Lilium Tower2687 · Al Barsha South Fifth · Jumeirah Village Triangle | Completed | 100% | Oct 2026 Completed | 266 | 124 |
| Al Jawhara Tower1782 · Al Barsha South Fifth · Jumeirah Village Triangle | Completed | 100% | Mar 2020 Completed | 532 | 113 |
| Blue Wave2165 · Wadi Al Safa 5 · Dubai Land Residence Complex | Completed | 100% | Jan 2023 Completed | 578 | 103 |
| The V Tower2199 · Wadi Al Safa 5 · Dubai Land Residence Complex | Completed | 100% | Sep 2023 Completed | 369 | 93 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 8, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.