Triplanet International (FZC) تراي بلانت انترناشونال(ش.م.ح) 7 projects in the DLD register: 7 completed, 0 under construction, 0 not started or pending. DLD projects register, export of 1 November 2026
Projects
7
in the DLD register
Completed
7
1,922 units delivered
Not yet completed
0
0 units in the pipeline
Delivery record
Projects: 7Completed 7
- Median time from start to completion: 54 months (7 completed projects).
- 1,922 units and villas in completed projects; 0 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 7 completed projects with both dates. In 7 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Triplanet International (FZC) Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Elite 6 Sports Residence330 · Al Hebiah Fourth · Dubai Sports City | Completed | 100% | Aug 2013 Completed | 366 | 73 |
| Elite Ii Sports Residence333 · Al Hebiah Fourth · Dubai Sports City | Completed | 100% | Nov 2012 Completed | 260 | 61 |
| Elite 3 Sports Residence331 · Al Hebiah Fourth · Dubai Sports City | Completed | 100% | Nov 2013 Completed | 315 | 59 |
| Elite Sports Residence328 · Al Hebiah Fourth · Dubai Sports City | Completed | 100% | Apr 2012 Completed | 248 | 49 |
| Elite 5 Sports Residence334 · Al Hebiah Fourth · Dubai Sports City | Completed | 100% | Mar 2014 Completed | 354 | 41 |
| Elite 4 Sports Residence332 · Al Hebiah Fourth · Dubai Sports City | Completed | 100% | Mar 2013 Completed | 251 | 30 |
| Elite 7 Sports Residence329 · Al Hebiah Fourth · Dubai Sports City | Completed | 100% | Jun 2014 Completed | 128 | 27 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.