Venus Properties Investment LTD فينوس بروبرتيز انفستمنت ليميتد 5 projects in the DLD register: 5 completed, 0 under construction, 0 not started or pending. DLD projects register, export of 1 November 2026
Projects
5
in the DLD register
Completed
5
77 units delivered
Not yet completed
0
0 units in the pipeline
Delivery record
Projects: 5Completed 5
- Median time from start to completion: 28 months (5 completed projects).
- 77 units and villas in completed projects; 0 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 5 completed projects with both dates. In 4 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Venus Properties Investment LTD Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Indigo Ville 3695 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Sep 2013 Completed | 18 | 3 |
| Indigo Ville 2694 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Jun 2014 Completed | 14 | 2 |
| Indigo Ville 1692 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Feb 2015 Completed | 15 | 2 |
| Indigo Ville 4696 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Dec 2012 Completed | 12 | 1 |
| Indigo Ville 8693 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Dec 2015 Completed | 18 | 1 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.