Zimaya Properties L.L.C زمايا للعقارات ذ.م.م 4 projects in the DLD register: 0 completed, 3 under construction, 1 not started or pending. 1 of the 3 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 4- 0 units and villas in completed projects; 560 in projects not yet completed.
- Under construction past their DLD end date: 1 of 3 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Zimaya Properties L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Belle Reve By Zimaya3027 · Al Barsha South Fourth · Jumeirah Village Circle | Under construction | 80.5% | Aug 2026 2 mo past | 2 mo | 190 | 156 |
| Belle Vie By Zimaya4023 · Nadd Hessa · Silicon Oasis | Under construction | 11% | Mar 2028 16 mo to go | — | 116 | 109 |
| Celeste Heights by Zimaya Properties3511 · Jabal Ali First · Al Furjan | Under construction | 41.2% | Sep 2027 10 mo to go | — | 71 | 63 |
| Lawncrest By Zimaya4491 · Me'Aisem First · International Media Production Zone | Not started | 0% | Jun 2029 31 mo to go | — | 183 | 29 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 4, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.