DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD master projectAl Thanyah First

Barsha Heights 6 of 18 phases not yet completed · 360 units · 198 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026

Barsha Heights has 18 projects in the Dubai Land Department projects register as of 1 November 2026: 6 not yet completed, with 360 units and villas. By DLD status: Under construction 2 · Completed 12 · Pending 4.

Phases
18
12 completed
Not yet completed
6
2 under construction
Units not yet completed
360
units and villas
Sales, 24 mo
198
registered with DLD

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Map of the phasesThe map shows 18 of the 18 phases: those with a map pin. Pins mark approximate locations.

The Chedi Private Residences · Under construction · Project locationMadison Residency · Completed · Project locationFahad 2 · Completed · Project locationTwo Towers · Completed · Project locationThe One Tower · Completed · Project locationTHE ONE by Prestige One · Under construction · Project locationProject 2713, Al Thanyah First · Pending · Project locationProject 4234, Al Thanyah First · Pending · Project locationProject 4307, Al Thanyah First · Pending · Project locationRove Home The Greens · Pending · Project locationIcon Tower · Completed · Project locationSmart Heights · Completed · Project locationExecutive Height · Completed · Project locationI - Rise Tower · Completed · Project locationMetro Central · Completed · Project locationGrand Central · Completed · Project locationSky Central · Completed · Project locationFirst Central · Completed · Project locationDubai Municipality · Makani
Under construction Pending Completed

Al Thanyah First (DM community)

Phases (18)Ordered by registered sales over 24 months

Phases (18)
ProjectDLD status Built DLD end date / completion To DLD end date Units Sales, 24 mo Since launch
The Chedi Private ResidencesUnder construction 2.6% Feb 2029 27 months to go 27 months to go 118 73 —
Madison ResidencyCompleted 100% Apr 2009 — 311 58 —
Fahad 2Completed 100% Aug 2016 — 234 36 —
Two TowersCompleted 100% Jul 2009 — 292 30 —
The One TowerCompleted 100% Aug 2014 — 191 1 —
THE ONE by Prestige OneUnder construction 7% Jun 2027 7 months to go 7 months to go 41 0 —
Project 2713, Al Thanyah FirstPending 33.1% — — 0 0 —
Project 4234, Al Thanyah FirstPending 0% Jun 2028 19 months to go 19 months to go 0 0 —
Project 4307, Al Thanyah FirstPending 4% Dec 2027 13 months to go 13 months to go 0 0 —
Rove Home The GreensPending 0% Dec 2029 37 months to go 37 months to go 201 0 —
Icon TowerCompleted 100% Jul 2009 — 66 0 —
Smart HeightsCompleted 100% Dec 2010 — 205 0 —
Executive HeightCompleted 100% Dec 2008 — 181 0 —
I - Rise TowerCompleted 100% Mar 2011 — 490 0 —
Metro CentralCompleted 100% May 2011 — 210 0 —
Grand CentralCompleted 100% Jul 2012 — 185 0 —
Sky CentralCompleted 100% Sep 2016 — 685 0 —
First CentralCompleted 0% Mar 2011 — 542 0 —

Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Units not yet completed, by DLD end year

6 phases
2027: 412028: 02029: 319No end date: 0

Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.

More on Barsha Heights

Own a unit in one of these phases? Track it free

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology