DAMAC Riverside 15 of 15 phases not yet completed · 7,049 units · 5,134 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
DAMAC Riverside has 15 projects in the Dubai Land Department projects register as of 1 November 2026: 15 not yet completed, with 7,049 units and villas. By DLD status: Under construction 15.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 15 of the 15 phases: those with a map pin. Pins mark approximate locations.
Dubai Investment Park Second (DM community)
Phases (15)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Damac Riverside Views - Capri 1 | Under construction | 8.2% | Mar 2029 28 months to go | 28 months to go | 824 | 805 | +0.4% |
| Damac Riverside Views - Azure 2 | Under construction | 5.8% | Mar 2029 28 months to go | 28 months to go | 720 | 695 | -1.5% |
| Damac Riverside Views - Capri 2 | Under construction | 8.3% | Mar 2029 28 months to go | 28 months to go | 576 | 475 | -1.9% |
| Damac Riverside Views - Indigo 1 | Under construction | 12.1% | Mar 2029 28 months to go | 28 months to go | 493 | 439 | -2.1% |
| Damac Riverside Views - Indigo 2 | Under construction | 12% | Mar 2029 28 months to go | 28 months to go | 388 | 346 | +3.7% |
| Damac Riverside Views - Marine 2 | Under construction | 12% | May 2028 18 months to go | 18 months to go | 358 | 279 | -5.5% |
| Damac Riverside Views - Marine 1 | Under construction | 11.8% | May 2028 18 months to go | 18 months to go | 358 | 275 | -3.5% |
| Damac Riverside Views - Marine 3 | Under construction | 18.2% | May 2028 18 months to go | 18 months to go | 276 | 267 | -1% |
| Damac Riverside Views - Marine 4 | Under construction | 21.2% | May 2028 18 months to go | 18 months to go | 276 | 259 | +1.7% |
| Damac Riverside Views - Royal 1 | Under construction | 14% | Mar 2029 28 months to go | 28 months to go | 335 | 258 | 0% |
| Damac Riverside Views - Royal 2 | Under construction | 13.5% | Mar 2029 28 months to go | 28 months to go | 335 | 258 | -0.2% |
| Damac Riverside - Lush | Under construction | 41.7% | Dec 2027 13 months to go | 13 months to go | 750 | 249 | +0.1% |
| Damac Riverside - Ivy | Under construction | 38.1% | Dec 2027 13 months to go | 13 months to go | 594 | 195 | +2.8% |
| Damac Riverside - Sage | Under construction | 13.3% | Dec 2027 13 months to go | 13 months to go | 558 | 167 | +3.7% |
| Damac Riverside - Olive | Under construction | 5.5% | Jun 2028 19 months to go | 19 months to go | 208 | 167 | +4.9% |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
15 phases| DLD end year | Projects | Units |
|---|---|---|
| 2027 | 3 | 1,902 |
| 2028 | 5 | 1,476 |
| 2029 | 7 | 3,671 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.