Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD master projectAl Thanyah Fifth

Jumeirah Islands 5 of 8 phases not yet completed · 4,161 units · 1,517 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026

Jumeirah Islands has 8 projects in the Dubai Land Department projects register as of 1 November 2026: 5 not yet completed, with 4,161 units and villas. By DLD status: Not started 1 · Under construction 3 · Completed 3 · Conditionally activating 1.

Phases
8
3 completed
Not yet completed
5
3 under construction
Units not yet completed
4,161
units and villas · 11
Sales, 24 mo
1,517
registered with DLD

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Map of the phasesThe map shows 8 of the 8 phases: those with a map pin. Pins mark approximate locations.

Eltiera Views · Not started / Conditionally activating · Approximate project locationSerenia District - West · Under construction · Project locationEltiera Heights · Under construction · Project locationSerenia District - East · Under construction · Approximate project locationJumeirah Heights Clusters · Completed · Approximate project locationTownhouses At Jumeirah Islands · Completed · Approximate project locationJumeirah Islands Mansions · Completed · Approximate project locationJumeirah Heights Fronds · Not started / Conditionally activating · Project locationDubai Municipality · Makani
Under construction Not started / Conditionally activating Completed Approximate project locations

Al Thanyah Fifth (DM community)

Phases (8)Ordered by registered sales over 24 months

Phases (8)
ProjectDLD status Built DLD end date / completion To DLD end date Units Sales, 24 mo Since launch
Eltiera ViewsNot started 0% Dec 2029 37 months to go 37 months to go 1,185 647 +6.3%
Serenia District - WestUnder construction 2.8% Dec 2028 25 months to go 25 months to go 423 378 -0.9%
Eltiera HeightsUnder construction 3% Dec 2028 25 months to go 25 months to go 357 303 -0.6%
Serenia District - EastUnder construction 1.1% Jun 2030 43 months to go 43 months to go 813 124 -3.2%
Jumeirah Heights ClustersCompleted 100% Feb 2012 — 246 43 —
Townhouses At Jumeirah IslandsCompleted 100% Apr 2016 — 0 14 —
Jumeirah Islands MansionsCompleted 100% Jan 2012 — 767 8 —
Jumeirah Heights FrondsConditionally activating 32.1% Jan 2013 166 months past it 166 months past it 1,383 0 —

Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Units not yet completed, by DLD end year

5 phases
2013: 1,3832028: 7802029: 1,1852030: 813

Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.

More on Jumeirah Islands

Own a unit in one of these phases? Track it free

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology