DLD master projectAl Kifaf
Wasl 1 5 of 7 phases not yet completed · 2,576 units · 1,337 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Wasl 1 has 7 projects in the Dubai Land Department projects register as of 1 November 2026: 5 not yet completed, with 2,576 units and villas. By DLD status: Under construction 3 · Completed 2 · Not started 2.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 7 of the 7 phases: those with a map pin. Pins mark approximate locations.
Al Kifaf (DM community)
Phases (7)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Avenue Park Towers | Under construction | 7.7% | Dec 2028 25 months to go | 25 months to go | 671 | 485 | -0.8% |
| Park Views Residences A | Under construction | 95.5% | — | — | 615 | 338 | +2.5% |
| 1 Residences | Completed | 100% | Sep 2022 | — | 758 | 173 | — |
| Park Views Residences B | Under construction | 98.8% | Mar 2027 4 months to go | 4 months to go | 476 | 152 | +7.6% |
| Park Gate Residences | Completed | 100% | Oct 2020 | — | 764 | 99 | — |
| Avenue Park Towers II | Not started | 0% | Mar 2030 40 months to go | 40 months to go | 596 | 90 | — |
| Nine Collective | Not started | 0% | Apr 2030 41 months to go | 41 months to go | 218 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
5 phases| DLD end year | Projects | Units |
|---|---|---|
| 2027 | 1 | 476 |
| 2028 | 1 | 671 |
| 2030 | 2 | 814 |
| No end date | 1 | 615 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Wasl 1
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology