DLD project no. 4245Under construction83 units
Ahs Tower ايه اتش اس تاور 67.4% built (DLD register as of 1 November 2026) · DLD end date Jan 2027 · 2 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

CompletionDLD readings of % built, beside the share of the planned period gone
% built and period elapsed
1 November 2026Two separate measures: one is DLD's % built, the other is time on the calendar.
| Date | % built | Source |
|---|---|---|
| 19 May 2026 | 67.4% | DLD inspection |
| 11 December 2025 | 60.2% | DLD inspection |
Source: Dubai Land Department projects register, as of 1 November 2026. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗ Period elapsed: our calculation from DLD’s start and end dates.
Our completion calculation
Pace since the last two DLD readings: —
Our calculation from DLD readings. It describes the recent pace only; it is not a forecast of the completion date.
Site timeline
± 6 monthsOur imagery reading holds no milestone for this project yet.
Our reading of historical satellite imagery
Changes in the DLD register
Source: DLD projects register exports, compared by CraneScore. Dates and progress are those in the Dubai Land Department projects register on each register date, not inspection dates. DLD can revise the end date; we keep every register reading from 28 October 2026 on and list the changes here.
Inspection photos and reports
DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.
CraneScore links to DLD and does not copy or host its photos or reports.
Building permits
Buildings on the project’s plots: 1, on construction permits: 1, as Dubai Municipality lists them.
| Work stage | Buildings |
|---|---|
| No stage listed | 1 |
Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.
DLD registration
DLD services ↗Description in the DLD register: The Tower configuration B+G+70F+R Office Tower situated along Sheikh Zayed Road, Dubai, United Arab Emirates, that involves selling 80 No. Shell & Core Office Units.
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
No off-plan sales are registered for this project since 2020, so there is no launch price.
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Rents in DLD area Trade Center Second
New Ejari rent contracts for apartments across DLD area Trade Center Second, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.
| Bedrooms | Median annual rent | New contracts | Change on a year earlier |
|---|---|---|---|
| Studio | AED 65,000 | 39 | -7.1% |
| 1 BR | AED 85,000 | 171 | -9.6% |
| 2 BR | AED 110,250 | 236 | -5.8% |
| 3 BR | AED 140,000 | 152 | 0% |
| 4 BR | AED 278,911 | 8 | -22.5% |
New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.
Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.
Looking for a unit in this or similar projects?
Tell us what you are looking for in Ahs Tower or similar projects. We reply by e-mail, and your request stays with CraneScore.
Estimated value range
Not enough registered off-plan sales for an estimate (at least 5 of one bedroom count in 12 months).
Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.
Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Jan 2027); move it with the slider.
A scenario from your own inputs, not this project's verified payment plan.
Common plans
Plan shares add up to 100% (must be 100%).
Payments per quarter
AED| Quarter | Paid |
|---|---|
| 2026-Q4 | AED 545,000 · AED 545,000 paid so far |
| 2027-Q1 | AED 500,000 · AED 1,045,000 paid so far |
Payments per quarter, AED, fees included. Illustration from your inputs.
The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.
Mortgage for a unit here
Questions about financing a unit in Ahs Tower? Leave your details and we reply by e-mail. Your request stays with CraneScore.
LocationTrade Center Second · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
School ratings: KHDA’s school directory ↗ · Report a wrong location
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 46, with 7,930 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2025 | 1 | 56 |
| 2026 | 14 | 1,489 |
| 2027 | 10 | 1,051 |
| 2028 | 13 | 1,746 |
| 2029 | 4 | 1,188 |
| 2030 | 2 | 1,826 |
| 2031 | 2 | 574 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Developer in DLD data Ahs Tower Holding Development L.L.C S.O.C · DLD developer no. 2539
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Questions about Ahs Tower
When is Ahs Tower's handover?
DLD lists an end date of Jan 2027 (register of 1 November 2026); the SPA sets the handover terms.
Is Ahs Tower past its DLD end date?
No. Its DLD end date is Jan 2027, 2 months after the register of 1 November 2026.
How far along is Ahs Tower?
67.4% built in the DLD register of 1 November 2026.
Who is the developer of Ahs Tower?
Ahs Tower Holding Development L.L.C S.O.C, as registered with DLD.
What is the DLD project number of Ahs Tower?
4245.