Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 4430Not started1,456 units

Greenz By Danube غرينز من دانوب Al Rowaiyah First by Danube Properties Development L.L.C DLD status: Not started (DLD register as of 1 November 2026) DLD end date Dec 2029 37 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

Campus buildings behind palm-lined hedges in Dubai International Academic City, Al Ruwayyah 1
Area photo: Al Rowaiyah First, not this project Photo: Mahmoud FarragCC BY 3.0
% built
0.1%
DLD register, 1 November 2026
Registered start
Jul 2026
DLD end date Dec 2029
Latest sales
2,731 AED/sqft
204 sales
3 BR estimate
3.40–3.75 M AED
Automated estimate, not a valuation
Developer
42 projects
19 completed · 8,200 units delivered

Completion

DLD status: Not started. 0.1% built, DLD end date 31 December 2029. DLD Project Status shows inspection reports once works begin.

DLD register readings
Date % built DLD end dateDLD status
28 October 2026 0.1% 31 December 2029Not started

Source: DLD projects register, export of 1 November 2026.

Inspection photos and reports

DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.

CraneScore links to DLD and does not copy or host its photos or reports.

DLD registration

DLD services ↗
DLD project number
4430
Escrow agent
Commercial Bank of Dubai(PSC)
Zoning authority
Dubai Development Authority (DDA)
DLD area
Al Rowaiyah First
Units · villas
0 · 1,456
Start → DLD end
Jul 2026 → Dec 2029
Registered units3 bed 486 · 4 bed 665 · 5+ bed 305; sizes 2,400–3,100 sqft

Homes: villas 1,456.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: 63 Cluster comprising of 1456 Townhouses.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

Fewer than 5 home sales after the launch window in the last 12 months, so no comparison is shown.

Prices are over villas and townhouses, the type most sales in this project are.

Median AED/sqft (number of sales) by bedroom count, where both periods have at least 5 sales
Bedrooms Launch price Latest registered sales Change
3 BR 2,647 (81) 2,647 (81) 0%
4 BR 3,159 (66) 3,159 (66) 0%
5 BR 2,717 (57) 2,717 (57) 0%
Registered sales of villas and townhouses by bedroom count over the last 24 months, and the median AED/sqft of the latest off-plan sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
3 BR 81 2,647 (81) May 2026 – Nov 2026
4 BR 66 3,159 (66) May 2026 – Nov 2026
5 BR 57 2,717 (57) May 2026 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2026-Q3 → 2026-Q4

Median AED/sqft of registered sales per quarter (villas and townhouses). Source: DLD. Grey dashed line: DLD area Al Rowaiyah First, median AED/sqft of off-plan sales of villas and townhouses by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 204 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
5 November 2026off-planVilla · 5 BR 2,507 8,131,032 3,243
5 November 2026off-planVilla · 3 BR 1,292 4,130,000 3,197
5 November 2026off-planVilla · 4 BR 1,292 4,019,906 3,111
5 November 2026off-planVilla · 3 BR 1,292 4,018,000 3,110
5 November 2026off-planVilla · 3 BR 1,489 3,827,806 2,571
5 November 2026off-planVilla · 3 BR 1,292 3,771,361 2,919
5 November 2026off-planVilla · 3 BR 1,292 3,674,000 2,844
5 November 2026off-planVilla · 3 BR 1,292 3,589,000 2,778
5 November 2026off-planVilla · 3 BR 1,292 3,550,000 2,748
5 November 2026off-planVilla · 3 BR 1,292 3,420,000 2,647

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Looking for a unit in this or similar projects?

Tell us what you are looking for in Greenz By Danube or similar projects. We reply by e-mail, and your request stays with CraneScore.

We send a 6-digit code to confirm it.
Bedrooms

Estimated value range

Estimated value range
Bedrooms Range, AED Based on Compared at
3 BR 3,400,000 – 3,750,000 81 sales, 12 months This project
4 BR 4,290,000 – 4,810,000 66 sales, 12 months This project
5 BR 5,680,000 – 6,960,000 57 sales, 12 months This project
Automated estimate, not a valuation

Estimate as of 5 November 2026 Track this unit

Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.

Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Dec 2029); move it with the slider.

A scenario from your own inputs, not this project's verified payment plan.

Common plans

Plan shares add up to 100% (must be 100%).

Handover
Dec 2029
Paid by handover
AED 1,045,000
Fees included
Price paid at handover
100%
Total cost
AED 1,045,000
Fees: AED 45,000

Payments per quarter

AED

Payments per quarter, AED, fees included. Illustration from your inputs.

The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.

Mortgage for a unit here

Questions about financing a unit in Greenz By Danube? Leave your details and we reply by e-mail. Your request stays with CraneScore.

We send a 6-digit code to confirm it.

LocationAl Rowaiyah First · Dubai Municipality community

Approximate project location© OpenStreetMap contributors · Dubai Municipality
Approximate project location

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

MallQ1 Mall · 2.8 km
SupermarketZoom Supermarket · 1.8 km
HospitalFakeeh University Hospital · 4.3 km
SchoolAmerican University in The Emirates · 2.1 km
Parkcommunity playpark · 2.7 km
BeachBeach · 6.1 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · © OpenStreetMap contributors

New homes within 1.5 km

Open projects within 1.5 km of the pin: 1, with 0 units and villas.

2029: 0

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Rowaiyah First: 1

Open projects in the same DLD area with a DLD end year from 2028 to 2030, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Tilal Binghatti 0% Dec 2029 — 9

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Rowaiyah First

Developer in DLD data Danube Properties Development L.L.C · DLD developer no. 1009

Projects registered
42
19 completed · 19 under construction · 4 not started
Units delivered
8,200
19,317 in the pipeline
Median build time
32 months
completed projects measured: 19
Past the DLD end date
4
of 11 under construction with a DLD end date

Completed a month or more after their DLD end date: 1 of 19 completed projects with both dates. In 11 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error