DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 1500Completed483 units

Reem - Mira Oasis Community Phase 3 ريم - ميرا أويس Al Yelayiss 1 by Al Aryam Phase Two L.L.C Completed 30 July 2019 (DLD) DLD end date Jan 2020 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Jul 2019
DLD end date Jan 2020
Build time
38 months
Jun 2016 → Jul 2019
Latest sales
987 AED/sqft
14 sales
3 BR rent
150,000 AED/yr
Gross yield 4.8% · 82 leases
Developer
3 projects
3 completed · 1,393 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3). Latest DLD inspection: 100% built on 19 January 2020 (inspections: 16).
Every DLD inspection and every change in the register %, newest first
Date % built Source
19 January 2020 100% DLD inspection
22 December 2019 98.7% DLD inspection
17 October 2019 93.7% DLD inspection
11 July 2019 82% DLD inspection
20 March 2019 77.8% DLD inspection
21 October 2018 68.9% DLD inspection
29 August 2018 66.1% DLD inspection
6 May 2018 51.8% DLD inspection
20 March 2018 43.3% DLD inspection
22 November 2017 25.4% DLD inspection
27 July 2017 14.2% DLD inspection
29 March 2017 12% DLD inspection
20 December 2016 10.1% DLD inspection
24 August 2016 7.3% DLD inspection
23 December 2015 7.3% DLD inspection
2 June 2015 1.6% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
44 monthsActual build
38 months
Start date
1 June 2016
DLD end date
19 January 2020
Completion date
30 July 2019
Completion vs DLD end date
5 months before

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
DLD project number
1500
Escrow agent
Dubai Islamic Bank (Public Joint Stock Company)
Zoning authority
Dubai Development Authority (DDA)
DLD area
Al Yelayiss 1
Units · villas
0 · 483
Start → DLD end
Jun 2016 → Jan 2020
Registered units3 bed 359 · 4 bed 124; sizes 2,281–2,553 sqft

Homes: villas 483.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Project consist of 483 freehold townhouses located in Al Yelayiss 1, Dubai, UAE. The villas are designed to have a concrete structure and block with internal and external finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

This project's first registered off-plan sale is before 1 March 2020, near the start of our sales data, so its launch may be older and no launch price is shown.

Prices are over villas and townhouses, the type most sales in this project are.

Registered sales of villas and townhouses by bedroom count over the last 24 months, and the median AED/sqft of the latest ready sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
3 BR 59 958 (9) May 2026 – Nov 2026
4 BR 34 1,183 (5) May 2026 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Skyline Index

Registered sale prices, rents and yields for Reem - Mira Oasis Community Phase 3, from DLD records.

Reem - Mira Oasis Community Phase 3: registered prices and rents on Skyline Index ↗

Median AED/sqft by quarter

2020-Q1 → 2026-Q4

Median AED/sqft of registered sales per quarter (villas and townhouses). Source: DLD. Grey dashed line: DLD area Al Yelayiss 1, median AED/sqft of ready sales of villas and townhouses by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents and gross yield

New Ejari rent contracts for villas and townhouses in this project, 12 months to 5 November 2026, against the 12 months before. Gross yield: the median annual rent over the median registered ready sale price of the same bedroom count in this project over the same 12 months.

Bedrooms Median annual rent New contracts Change on a year earlier Gross yield
3 BR AED 150,000 82 -6.2% 4.8%
4 BR AED 175,000 24 -8.9% —

Gross yield is before service charges, other costs and empty months.

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 38; registered amount AED 89.5M.

Since the first registration in 2017-Q2: 336 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 25 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
20 October 2026readyVilla · 4 BR 3,773 3,520,000 933
19 October 2026readyVilla · 3 BR 2,424 3,700,000 1,526
9 October 2026readyVilla · 3 BR 2,958 2,600,000 879
1 October 2026readyVilla · 4 BR 2,317 3,300,000 1,424
17 September 2026readyVilla · 3 BR 3,856 3,400,000 882
10 September 2026readyVilla · 4 BR 3,550 4,200,000 1,183
13 August 2026readyVilla · 4 BR 2,297 3,375,000 1,469
6 August 2026readyVilla · 3 BR 2,818 2,700,000 958
24 July 2026readyVilla · 3 BR 2,969 2,675,000 901
22 July 2026readyVilla · 3 BR 2,365 2,625,000 1,110

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationAl Yalayis 1 · Dubai Municipality community

Mira Oasis 3 Park · 220 mPark · 410 mPark · 580 mSpinneys · 700 mSpinneys · 1 kmSpinneys · 1 kmApproximate project location© OpenStreetMap contributors · Dubai Municipality · Makani
Approximate project location Malls and supermarkets Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

MallMall · 5.3 km
SupermarketSpinneys · 700 m
SchoolGems Metropole School · 2.9 km
ParkMira Oasis 3 Park · 220 m

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors

New homes within 1.5 km

Open projects within 1.5 km of the pin: 14, with 2,558 units and villas.

2027: 5122028: 5342029: 540No end date: 972

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Yalayis 1: 30

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Damac Islands 2 - Bahamas 2 0.3% Jun 2030 1,796 509
Damac Islands 2 - Bahamas 1 0.3% Jun 2030 1,822 465
Damac Islands 2 - Cuba 0.2% Jun 2030 1,648 447
Damac Islands 2 - Bermuda 0.2% Jun 2030 1,680 425
Damac Islands 2 - Tahiti 2 0.3% Jun 2030 1,932 392
Damac Islands 2 - Maui 0.2% Jun 2030 2,029 357
Damac Islands 2 - Barbados 1 0.2% Jun 2030 1,822 327
Damac Islands 2 - Barbados 2 0.2% Jun 2030 1,873 279
Damac Islands 2 - Tahiti 1 0.3% Jun 2030 1,619 263
Damac Islands 2 - Antigua 1 0.3% Dec 2030 1,932 210
Damac Islands - Maldives 2 14.1% Dec 2028 — 3
Damac Islands - Bora Bora 3 4.2% Dec 2028 — 2

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Yalayis 1

Developer in DLD data Al Aryam Phase Two L.L.C · DLD developer no. 994

Projects registered
3
3 completed · 0 under construction · 0 not started
Units delivered
1,393
0 in the pipeline
Median build time
39 months
completed projects measured: 3

Completed a month or more after their DLD end date: 0 of 3 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Questions about Reem - Mira Oasis Community Phase 3

When was Reem - Mira Oasis Community Phase 3 completed?

Reem - Mira Oasis Community Phase 3 is recorded as completed on 30 July 2019 (DLD register of 1 November 2026).

Who is the developer of Reem - Mira Oasis Community Phase 3?

Al Aryam Phase Two L.L.C, as registered with DLD.

What is the DLD project number of Reem - Mira Oasis Community Phase 3?

1500.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error