DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026

51–59 of 59 projects, most registered sales in 24 months first

51–59 of 59 projects, most registered sales in 24 months first
Project Developer DLD status Built DLD end date Sales, 24 mo
Azizi Jewel3020 · Jabal Ali First · Al FurjanAzizi Developments L.L.C Under construction 43% — 0
Azizi Neila3203 · Jabal Ali First · Al FurjanAzizi Developments L.L.C Under construction 38.5% Jul 2027 8 mo to go 0
Azizi Riviera 533615 · Al Merkadh · Meydan One CommunityAzizi Developments L.L.C Under construction 63.2% Mar 2027 4 mo to go 0
Azizi Riviera 543739 · Al Merkadh · Meydan One CommunityAzizi Developments L.L.C Under construction 74.6% May 2027 6 mo to go 0
Azizi Riviera 623619 · Al Merkadh · Meydan One CommunityAzizi Developments L.L.C Under construction 90.8% Mar 2027 4 mo to go 0
Azizi Riviera 643794 · Al Merkadh · Meydan One CommunityAzizi Developments L.L.C Under construction 83.8% May 2027 6 mo to go 0
Azizi Sikander3845 · Jabal Ali First · Al FurjanAzizi Developments L.L.C Under construction 2% Jun 2027 7 mo to go 0
Jadaf Beach Oasis4402 · Al Jadaf · Sama Al JadafAzizi Developments L.L.C Pending 0% Feb 2029 27 mo to go 0
Wasl by Azizi3563 · Palm DeiraAzizi Developments L.L.C Under construction 2% Feb 2028 15 mo to go 0

How to read this list

DLD status
Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
Built
The latest % complete that DLD publishes for the project.
DLD end date
The completion date in the DLD register, with whole months to go from the export date.
Past DLD end date
Whole months since the DLD end date, for projects DLD still lists as under construction.
Sales, 24 mo
Sales of units in the project registered with DLD in the last 24 months.