Azizi Developments L.L.C عزيزي ديفليوبمنتس ش.ذ.م.م 150 projects in the DLD register: 91 completed, 43 under construction, 16 not started or pending. 10 of the 38 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 150- Median time from start to completion: 56 months (91 completed projects).
- 20,380 units and villas in completed projects; 40,083 in projects not yet completed.
- Completed a month or more after their DLD end date: 13 of 90 completed projects with both dates. In 65 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 10 of 38 projects with an end date, by a median of 10 months.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Azizi Developments L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Azizi Venice 143073 · Madinat Al Mataar · Dubai World Central | Under construction | 30.3% | May 2026 5 mo past | 5 mo | 3,438 | 2,546 |
| Azizi Venice 63474 · Madinat Al Mataar · Dubai World Central | Under construction | 11.6% | Dec 2027 13 mo to go | — | 2,965 | 1,302 |
| Azizi Venice 72956 · Madinat Al Mataar · Dubai World Central | Under construction | 29.2% | Jan 2026 9 mo past | 9 mo | 2,276 | 1,180 |
| Azizi Venice 153741 · Madinat Al Mataar · Dubai World Central | Not started | 0% | May 2027 6 mo to go | — | 1,855 | 904 |
| Azizi Milan Heights4079 · Wadi Al Safa 4 · City Of Arabia | Not started | 0% | Sep 2028 22 mo to go | — | 2,852 | 829 |
| azizi venice 133297 · Madinat Al Mataar · Dubai World Central | Under construction | 45.9% | Sep 2027 10 mo to go | — | 1,888 | 797 |
| Azizi Venice 102955 · Madinat Al Mataar · Dubai World Central | Under construction | 36.3% | — | — | 1,263 | 776 |
| azizi venice 123318 · Madinat Al Mataar · Dubai World Central | Under construction | 21.6% | Sep 2027 10 mo to go | — | 1,428 | 753 |
| Azizi Venice 113239 · Madinat Al Mataar · Dubai World Central | Under construction | 25.9% | Aug 2027 9 mo to go | — | 1,094 | 696 |
| Azizi Mirage 12034 · Al Hebiah Second · Dubai Studio City | Completed | 100% | Oct 2025 Completed | — | 762 | 637 |
| Beach Oasis 23043 · Al Hebiah Second · Dubai Studio City | Under construction | 53.2% | Apr 2026 6 mo past | 6 mo | 704 | 466 |
| Azizi Venice 92829 · Madinat Al Mataar · Dubai World Central | Under construction | 54% | — | — | 778 | 428 |
| Azizi Milan 203662 · Wadi Al Safa 4 · City Of Arabia | Not started | 0% | Apr 2027 5 mo to go | — | 741 | 394 |
| Azizi Milan 303656 · Wadi Al Safa 4 · City Of Arabia | Not started | 0% | Apr 2027 5 mo to go | — | 780 | 386 |
| Azizi Venice 82830 · Madinat Al Mataar · Dubai World Central | Under construction | 53% | — | — | 778 | 372 |
| Azizi Venice 163814 · Madinat Al Mataar · Dubai World Central | Not started | 0% | Jun 2027 7 mo to go | — | 1,055 | 310 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 59, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.