DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026

1–10 of 10 projects, most registered sales in 24 months first

1–10 of 10 projects, most registered sales in 24 months first
Project Developer DLD status Built DLD end date Past DLD end date Sales, 24 mo
Azizi Venice 143073 · Madinat Al Mataar · Dubai World CentralAzizi Developments L.L.C Under construction 30.3% May 2026 5 mo past5 mo 2,546
Azizi Venice 72956 · Madinat Al Mataar · Dubai World CentralAzizi Developments L.L.C Under construction 29.2% Jan 2026 9 mo past9 mo 1,180
Beach Oasis 23043 · Al Hebiah Second · Dubai Studio CityAzizi Developments L.L.C Under construction 53.2% Apr 2026 6 mo past6 mo 466
Azizi Venice 52822 · Madinat Al Mataar · Dubai World CentralAzizi Developments L.L.C Under construction 63.5% Oct 2025 12 mo past12 mo 309
Azizi Grand2036 · Al Hebiah Fourth · Dubai Sports CityAzizi Developments L.L.C Under construction 82.1% Feb 2025 20 mo past20 mo 290
Azizi Venice 22820 · Madinat Al Mataar · Dubai World CentralAzizi Developments L.L.C Under construction 57.2% Dec 2025 10 mo past10 mo 264
Azizi Venice 42800 · Madinat Al Mataar · Dubai World CentralAzizi Developments L.L.C Under construction 62.2% Dec 2025 10 mo past10 mo 167
Azizi Riviera Reve2434 · Al Merkadh · Meydan One CommunityAzizi Developments L.L.C Under construction 76.6% Feb 2025 20 mo past20 mo 144
Azizi Venice 32799 · Madinat Al Mataar · Dubai World CentralAzizi Developments L.L.C Under construction 76% Dec 2025 10 mo past10 mo 83
Azizi Venice 12821 · Madinat Al Mataar · Dubai World CentralAzizi Developments L.L.C Under construction 67.4% Dec 2025 10 mo past10 mo 66

How to read this list

DLD status
Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
Built
The latest % complete that DLD publishes for the project.
DLD end date
The completion date in the DLD register, with whole months to go from the export date.
Past DLD end date
Whole months since the DLD end date, for projects DLD still lists as under construction.
Sales, 24 mo
Sales of units in the project registered with DLD in the last 24 months.