Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026

1–18 of 18 projects, most registered sales in 24 months first

1–18 of 18 projects, most registered sales in 24 months first
Project Developer DLD status Built DLD end date Sales, 24 mo
Palm Jebel Ali - Frond A3331 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 11.1% Jan 2028 14 mo to go 0
Palm Jebel Ali - Frond B3347 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 10% Jan 2028 14 mo to go 0
Palm Jebel Ali - Frond C3353 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 8.6% Jan 2028 14 mo to go 0
Palm Jebel Ali - Frond D3395 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 8.7% Jan 2028 14 mo to go 0
Palm Jebel Ali - Frond E3352 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 9.2% Jan 2028 14 mo to go 0
Palm Jebel Ali - Frond F3354 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 11.8% Jan 2028 14 mo to go 0
Palm Jebel Ali - Frond K2596 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 47.9% Dec 2027 13 mo to go 0
Palm Jebel Ali - Frond L2595 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 42.7% — 0
Palm Jebel Ali - Frond M2594 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 40.3% Oct 2027 11 mo to go 0
Palm Jebel Ali - Frond N2593 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 47.1% Oct 2027 11 mo to go 0
Palm Jebel Ali - Frond O2592 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 55.7% Sep 2027 10 mo to go 0
Palm Jebel Ali - Frond P2590 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 34.7% Sep 2027 10 mo to go 0
Palm Jebel Ali - The Beach and Coral Collection4091 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 2.4% Dec 2028 25 mo to go 0
Palm Jebel Ali - The Beach and Coral Collection - Frond B4101 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 2.7% Dec 2028 25 mo to go 0
Palm Jebel Ali - The Beach and Coral Collection - Frond C4103 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 2.8% Dec 2028 25 mo to go 0
Palm Jebel Ali - The Beach and Coral Collection - Frond D4107 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 2.2% Dec 2028 25 mo to go 0
Palm Jebel Ali - The Beach and Coral Collection - Frond E4113 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 2.6% Dec 2028 25 mo to go 0
Palm Jebel Ali - The Beach and Coral Collection - Frond F4128 · Palm Jabal AliThe Palm - Jebel Ali CO. (L.L.C) Under construction 2.5% Dec 2028 25 mo to go 0

How to read this list

DLD status
Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
Built
The latest % complete that DLD publishes for the project.
DLD end date
The completion date in the DLD register, with whole months to go from the export date.
Past DLD end date
Whole months since the DLD end date, for projects DLD still lists as under construction.
Sales, 24 mo
Sales of units in the project registered with DLD in the last 24 months.