Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026
| Project | Developer | DLD status | Built | DLD end date | Past DLD end date | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Binghatti Elite3341 · Me'Aisem First · International Media Production Zone | Binghatti Developers FZE | Under construction | 53.3% | Jun 2026 4 mo past | 4 mo | 1,793 |
| Binghatti Hillviews3321 · Al Barshaa South Second · Dubai Science Park | Binghatti Developers FZE | Under construction | 32.6% | Apr 2026 7 mo past | 7 mo | 1,556 |
| Binghatti Skyhall3504 · Business Bay | Binghatti Developers FZE | Under construction | 31.1% | Aug 2026 2 mo past | 2 mo | 648 |
| Binghatti Amberhall3552 · Al Barsha South Fourth · Jumeirah Village Circle | Binghatti Developers FZE | Under construction | 70% | Feb 2026 8 mo past | 8 mo | 623 |
| One by Binghatti3107 · Business Bay | Binghatti Developers FZE | Under construction | 50.2% | May 2026 5 mo past | 5 mo | 574 |
| Binghatti Ruby3533 · Al Barsha South Fourth · Jumeirah Village Circle | Binghatti Developers FZE | Under construction | 65% | Feb 2026 8 mo past | 8 mo | 552 |
| Binghatti Haven3442 · Al Hebiah Fourth · Dubai Sports City | Binghatti Developers FZE | Under construction | 76.1% | Mar 2026 7 mo past | 7 mo | 485 |
| Binghatti Starlight3195 · Al Jadaf · Dubai Health Care City Phase 2 | Binghatti Developers FZE | Under construction | 63.1% | Mar 2026 7 mo past | 7 mo | 481 |
| Binghatti Hillside3481 · Al Barshaa South Second · Dubai Science Park | Binghatti Developers FZE | Under construction | 80% | Jun 2026 4 mo past | 4 mo | 356 |
| Binghatti Moonlight3722 · Al Jadaf · Jaddaf Waterfront | Binghatti Developers FZE | Under construction | 19.2% | Jun 2026 4 mo past | 4 mo | 227 |
| Binghatti Twilight3397 · Al Jadaf · Jaddaf Waterfront | Binghatti Developers FZE | Under construction | 55.4% | Apr 2026 6 mo past | 6 mo | 221 |
| Burj Binghatti Jacob & Co. Residences2480 · Business Bay | Binghatti Developers FZE | Under construction | 52.1% | Jun 2026 4 mo past | 4 mo | 95 |
| Bugatti Residences by Binghatti2547 · Business Bay | Binghatti Developers FZE | Under construction | 65.6% | Dec 2025 10 mo past | 10 mo | 94 |
How to read this list
- DLD status
- Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
- Built
- The latest % complete that DLD publishes for the project.
- DLD end date
- The completion date in the DLD register, with whole months to go from the export date.
- Past DLD end date
- Whole months since the DLD end date, for projects DLD still lists as under construction.
- Sales, 24 mo
- Sales of units in the project registered with DLD in the last 24 months.