DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026

1–13 of 13 projects, most registered sales in 24 months first

1–13 of 13 projects, most registered sales in 24 months first
Project Developer DLD status Built DLD end date / completion Sales, 24 mo
The Pulse Beachfront 32367 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Completed 100% Apr 2025 Completed 120
The Pulse- Beachfront2306 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Completed 100% Dec 2024 Completed 117
The Pulse Beachfront 22328 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Completed 100% Dec 2024 Completed 62
The Pulse Residence1805 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Completed 100% Jun 2019 Completed 48
The Pulse Residence Plaza1883 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Completed 100% Mar 2021 Completed 43
The Pulse Townhouses1804 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Completed 100% Feb 2020 Completed 36
The Pulse Residence Park1830 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Completed 100% Mar 2020 Completed 30
The Pulse Boulevard Apartments1806 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Completed 100% Dec 2019 Completed 29
The Pulse Villas1944 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Completed 100% Jun 2023 Completed 28
The Pulse Boulevard Apartments - C31884 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Completed 100% Mar 2020 Completed 23
The Pulse Boulevard Apartments-C11828 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Completed 100% Apr 2020 Completed 23
The Pulse Residence Icon1829 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Completed 100% Jan 2020 Completed 17
The Pulse Villas 22279 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Completed 100% Jan 2024 Completed 8

How to read this list

DLD status
Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
Built
The latest % complete that DLD publishes for the project.
DLD end date
The completion date in the DLD register, with whole months to go from the export date.
Past DLD end date
Whole months since the DLD end date, for projects DLD still lists as under construction.
Sales, 24 mo
Sales of units in the project registered with DLD in the last 24 months.