Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026

1–21 of 21 projects, most registered sales in 24 months first

1–21 of 21 projects, most registered sales in 24 months first
Project Developer DLD status Built DLD end date Past DLD end date Sales, 24 mo
South Square3711 · Madinat Al Mataar · Dubai World CentralDubai South Properties DWC LLC Under construction 2.6% Jun 2028 19 mo to go— 428
Hayat 44038 · Madinat Al Mataar · Dubai World CentralDubai South Properties DWC LLC Under construction 4.5% Jul 2028 20 mo to go— 194
Hayat 23809 · Madinat Al Mataar · Dubai World CentralDubai South Properties DWC LLC Under construction 2% May 2028 18 mo to go— 142
Beachfront Gates 23379 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Under construction 41.7% Dec 2026 1 mo to go— 141
Hayat 33810 · Madinat Al Mataar · Dubai World CentralDubai South Properties DWC LLC Under construction 3.9% May 2028 18 mo to go— 141
Hayat 14422 · Madinat Al Mataar · Dubai World CentralDubai South Properties DWC LLC Not started 0% Mar 2029 28 mo to go— 117
Hayat 54053 · Madinat Al Mataar · Dubai World CentralDubai South Properties DWC LLC Not started 0% Jul 2028 20 mo to go— 109
Hayat 64423 · Madinat Al Mataar · Dubai World CentralDubai South Properties DWC LLC Not started 0% Mar 2029 28 mo to go— 93
South Living1946 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Under construction 88.8% Feb 2020 80 mo past80 mo 86
South Bay 5 Premium2985 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Under construction 77.8% — — 45
South Bay 3 Premium2711 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Under construction 88.4% — — 43
South Bay 12452 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Under construction 93.7% Mar 2025 19 mo past19 mo 38
South Bay 22584 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Under construction 93.8% May 2026 5 mo past5 mo 35
South Bay 4 Premium2844 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Under construction 85.5% — — 31
Hayat 74424 · Madinat Al Mataar · Dubai World CentralDubai South Properties DWC LLC Not started 0% Mar 2029 28 mo to go— 29
South Bay 6 Premium3051 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Under construction 82.1% — — 29
Project 4609, Madinat Al Mataar4609 · Madinat Al Mataar · Dubai World CentralDubai South Properties DWC LLC Pending 0% Apr 2030 41 mo to go— 0
Project 4612, Madinat Al Mataar4612 · Madinat Al Mataar · Dubai World CentralDubai South Properties DWC LLC Pending 0% Apr 2030 41 mo to go— 0
Beachfront Gates 13377 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Under construction 36.3% Dec 2026 1 mo to go— 0
Beachfront Gates 34580 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Not started 0% May 2029 30 mo to go— 0
The Pulse Boulevard Grove1885 · Madinat Al Mataar · Dubai South Residential DistrictDubai South Properties DWC LLC Pending 0% Sep 2019 — 0

How to read this list

DLD status
Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
Built
The latest % complete that DLD publishes for the project.
DLD end date
The completion date in the DLD register, with whole months to go from the export date.
Past DLD end date
Whole months since the DLD end date, for projects DLD still lists as under construction.
Sales, 24 mo
Sales of units in the project registered with DLD in the last 24 months.