DLD project no. 1885Pending108 units
The Pulse Boulevard Grove النبض جادة البستان DLD status: Pending (DLD register as of 1 November 2026) · DLD end date Sep 2019 · past its DLD end date by 86 months DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.
Completion
DLD status: Pending. 0% built, DLD end date 1 September 2019. DLD Project Status shows inspection reports once works begin.
| Date | % built | DLD end date | DLD status |
|---|---|---|---|
| 28 October 2026 | 0% | 1 September 2019 | Pending |
| 12 May 2024 | 0% | 1 September 2019 | Frozen |
| 5 August 2022 | 0% | 1 September 2019 | Frozen |
Source: DLD projects register, export of 1 November 2026.
DLD registration
DLD services ↗Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: One building composed as followed: Basement (parking and services) + Ground floor Parking and Services + 11 Apartments floors 1 pool deck on the podium level 1 gym and changing room on podium level 1 kid?s play room on podium level
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
LocationMadinat Al Mataar · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 89, with 8,077 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2020 | 1 | 209 |
| 2025 | 2 | 113 |
| 2026 | 16 | 954 |
| 2027 | 31 | 1,708 |
| 2028 | 26 | 2,749 |
| 2029 | 11 | 2,054 |
| 2030 | 1 | 290 |
| No end date | 1 | 0 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Madinat Al Mataar: 167
Open projects in the same DLD area with a DLD end year from 2018 to 2020, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| South Living | 88.8% | Feb 2020 | 1,314 | 86 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Dubai South Properties DWC LLC · DLD developer no. 1142
Completed a month or more after their DLD end date: 0 of 13 completed projects with both dates. In 9 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error