Madinat Al Mataar مدينة المطار 168 projects not yet completed · 45,858 units · 24,762 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Madinat Al Mataar has 168 projects not yet completed in the Dubai Land Department projects register as of 1 November 2026, with 45,858 units and villas; its projects had 24,762 registered sales in the last 24 months.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Projects on the map100 of the 100 projects listed have a map pin.
Projects not yet completed (100)Projects not yet completed in Madinat Al Mataar, by registered sales in 24 months
| Project | Developer | DLD status | Built | DLD end date | Past DLD end date | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Azizi Venice 143073 · Madinat Al Mataar · Dubai World Central | Azizi Developments L.L.C | Under construction | 30.3% | May 2026 5 mo past | 5 mo | 2,546 |
| Azizi Venice 63474 · Madinat Al Mataar · Dubai World Central | Azizi Developments L.L.C | Under construction | 11.6% | Dec 2027 13 mo to go | — | 1,302 |
| Azizi Venice 72956 · Madinat Al Mataar · Dubai World Central | Azizi Developments L.L.C | Under construction | 29.2% | Jan 2026 9 mo past | 9 mo | 1,180 |
| Terra Heights3381 · Madinat Al Mataar · Expo City | DWTC Emaar L.L.C | Under construction | 9.1% | Mar 2029 28 mo to go | — | 1,017 |
| Azizi Venice 153741 · Madinat Al Mataar · Dubai World Central | Azizi Developments L.L.C | Not started | 0% | May 2027 6 mo to go | — | 904 |
| azizi venice 133297 · Madinat Al Mataar · Dubai World Central | Azizi Developments L.L.C | Under construction | 45.9% | Sep 2027 10 mo to go | — | 797 |
| Azizi Venice 102955 · Madinat Al Mataar · Dubai World Central | Azizi Developments L.L.C | Under construction | 36.3% | — | — | 776 |
| azizi venice 123318 · Madinat Al Mataar · Dubai World Central | Azizi Developments L.L.C | Under construction | 21.6% | Sep 2027 10 mo to go | — | 753 |
| Azizi Venice 113239 · Madinat Al Mataar · Dubai World Central | Azizi Developments L.L.C | Under construction | 25.9% | Aug 2027 9 mo to go | — | 696 |
| Terra Gardens4160 · Madinat Al Mataar · Expo City | DWTC Emaar L.L.C | Not started | 0.1% | Oct 2029 35 mo to go | — | 544 |
| Terra Woods4367 · Madinat Al Mataar · Expo City | DWTC Emaar L.L.C | Not started | 0% | Mar 2030 40 mo to go | — | 505 |
| Azizi Venice 92829 · Madinat Al Mataar · Dubai World Central | Azizi Developments L.L.C | Under construction | 54% | — | — | 428 |
| South Square3711 · Madinat Al Mataar · Dubai World Central | Dubai South Properties DWC LLC | Under construction | 2.6% | Jun 2028 19 mo to go | — | 428 |
| Expo City Sidr Residences3308 · Madinat Al Mataar · Expo City | Expo City Sidr Residences Development FZCO | Under construction | 25% | Mar 2028 16 mo to go | — | 423 |
| Windsor House4035 · Madinat Al Mataar · Dubai South Residential District | Ellington Sb Development L.L.C | Under construction | 3.1% | Jul 2029 32 mo to go | — | 399 |
| Windsor House Ii4300 · Madinat Al Mataar · Dubai South Residential District | Ellington Properties Development L.L.C | Under construction | 0.6% | Jul 2029 32 mo to go | — | 392 |
| Azizi Venice 82830 · Madinat Al Mataar · Dubai World Central | Azizi Developments L.L.C | Under construction | 53% | — | — | 372 |
| Azizi Venice 163814 · Madinat Al Mataar · Dubai World Central | Azizi Developments L.L.C | Not started | 0% | Jun 2027 7 mo to go | — | 310 |
| Azizi Venice 52822 · Madinat Al Mataar · Dubai World Central | Azizi Developments L.L.C | Under construction | 63.5% | Oct 2025 12 mo past | 12 mo | 309 |
| Expo City Al Waha Residences 013523 · Madinat Al Mataar · Expo City | Expo City Al Waha Residences Development FZCO | Under construction | 65.8% | Jun 2027 7 mo to go | — | 286 |
| Expo City Al Waha Residences 023567 · Madinat Al Mataar · Expo City | Expo City Al Waha Residences Development FZCO | Under construction | 61.4% | Jun 2027 7 mo to go | — | 273 |
| Azizi Venice 22820 · Madinat Al Mataar · Dubai World Central | Azizi Developments L.L.C | Under construction | 57.2% | Dec 2025 10 mo past | 10 mo | 264 |
| Expo Valley Views4007 · Madinat Al Mataar · Dubai World Central | Expo City Valley Apartments FZCO | Not started | 0% | Oct 2029 35 mo to go | — | 255 |
| Greenspoint 23558 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Under construction | 40.1% | Mar 2029 28 mo to go | — | 245 |
| Golf Vale4416 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Not started | 0% | Mar 2030 40 mo to go | — | 238 |
| Waada - Altura 24085 · Madinat Al Mataar · Dubai World Central | Bt Properties DWC LLC | Under construction | 7.2% | Mar 2029 28 mo to go | — | 237 |
| AVENEW888-LOOM4293 · Madinat Al Mataar · Dubai South Residential District | Avenew Real Estate Development L.L.C | Under construction | 1.6% | Mar 2028 16 mo to go | — | 228 |
| Waada - Altura 14163 · Madinat Al Mataar · Dubai World Central | Bt Properties DWC LLC | Under construction | 1.9% | Apr 2029 29 mo to go | — | 222 |
| Greenspoint3514 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Under construction | 42.9% | Mar 2029 28 mo to go | — | 197 |
| Hayat 44038 · Madinat Al Mataar · Dubai World Central | Dubai South Properties DWC LLC | Under construction | 4.5% | Jul 2028 20 mo to go | — | 194 |
| Golf Meadow3579 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Under construction | 4.5% | Jul 2029 32 mo to go | — | 183 |
| AVENEW888 - Modo3828 · Madinat Al Mataar · Dubai South Residential District | Avenew Real Estate Development L.L.C | Under construction | 21.2% | Mar 2028 16 mo to go | — | 183 |
| Greenridge3283 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Under construction | 35.6% | Dec 2028 25 mo to go | — | 182 |
| Golf Dale3427 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Not started | 0.3% | Dec 2028 25 mo to go | — | 182 |
| Golf Hills 24119 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Under construction | 4.2% | Sep 2029 34 mo to go | — | 181 |
| Golf Fields4415 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Not started | 0% | Feb 2030 39 mo to go | — | 181 |
| Waada - Cascada 13731 · Madinat Al Mataar · Dubai World Central | Bt Properties DWC LLC | Under construction | 1.6% | Oct 2028 23 mo to go | — | 178 |
| Golf Hills4117 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Under construction | 3.7% | Sep 2029 34 mo to go | — | 178 |
| Golf Verge3578 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Under construction | 4.2% | May 2029 30 mo to go | — | 177 |
| Golf Edge3385 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Not started | 0% | Feb 2029 27 mo to go | — | 168 |
| Azizi Venice 42800 · Madinat Al Mataar · Dubai World Central | Azizi Developments L.L.C | Under construction | 62.2% | Dec 2025 10 mo past | 10 mo | 167 |
| Vista Ridge4201 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Not started | 0% | Sep 2029 34 mo to go | — | 161 |
| Grove Ridge4200 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Not started | 0% | Sep 2029 34 mo to go | — | 160 |
| Greenville 23319 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Under construction | 47.3% | Mar 2029 28 mo to go | — | 150 |
| Waada - Rayhan 13730 · Madinat Al Mataar · Dubai World Central | Bt Properties DWC LLC | Under construction | 15.1% | Oct 2028 23 mo to go | — | 144 |
| Hayat 23809 · Madinat Al Mataar · Dubai World Central | Dubai South Properties DWC LLC | Under construction | 2% | May 2028 18 mo to go | — | 142 |
| Beachfront Gates 23379 · Madinat Al Mataar · Dubai South Residential District | Dubai South Properties DWC LLC | Under construction | 41.7% | Dec 2026 1 mo to go | — | 141 |
| Hayat 33810 · Madinat Al Mataar · Dubai World Central | Dubai South Properties DWC LLC | Under construction | 3.9% | May 2028 18 mo to go | — | 141 |
| Greenville3316 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Under construction | 46% | Mar 2029 28 mo to go | — | 140 |
| Enre Residence By Imtiaz4336 · Madinat Al Mataar · Dubai South Residential District | Imtiaz South Real Estate Development L.L.C | Under construction | 14.6% | Aug 2028 21 mo to go | — | 133 |
| Hayat 14422 · Madinat Al Mataar · Dubai World Central | Dubai South Properties DWC LLC | Not started | 0% | Mar 2029 28 mo to go | — | 117 |
| Golf Acres3426 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Under construction | 3.5% | Dec 2028 25 mo to go | — | 113 |
| Hayat 54053 · Madinat Al Mataar · Dubai World Central | Dubai South Properties DWC LLC | Not started | 0% | Jul 2028 20 mo to go | — | 109 |
| Golf Trails4523 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Not started | 0% | Oct 2030 47 mo to go | — | 97 |
| Hayat 64423 · Madinat Al Mataar · Dubai World Central | Dubai South Properties DWC LLC | Not started | 0% | Mar 2029 28 mo to go | — | 93 |
| Golf Point3215 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Under construction | 4.8% | Oct 2028 23 mo to go | — | 87 |
| South Living1946 · Madinat Al Mataar · Dubai South Residential District | Dubai South Properties DWC LLC | Under construction | 88.8% | Feb 2020 80 mo past | 80 mo | 86 |
| The Harmony3130 · Madinat Al Mataar · Dubai South Residential District | Al Mizan Harmony Development L.L.C | Under construction | 97.8% | Oct 2025 12 mo past | 12 mo | 84 |
| Waada - Cascada 23732 · Madinat Al Mataar · Dubai World Central | Bt Properties DWC LLC | Not started | 0% | Mar 2029 28 mo to go | — | 84 |
| Azizi Venice 32799 · Madinat Al Mataar · Dubai World Central | Azizi Developments L.L.C | Under construction | 76% | Dec 2025 10 mo past | 10 mo | 83 |
| Expo City Mangrove Residences2612 · Madinat Al Mataar · Expo City | Expo City Mangrove Residences Development FZCO | Under construction | 91.2% | Jan 2026 9 mo past | 9 mo | 80 |
| Marquis Horizon4372 · Madinat Al Mataar · Dubai South Residential District | Marquis Home Developer L.L.C | Not started | 0% | Sep 2028 22 mo to go | — | 80 |
| Golden Woods Albab Views3591 · Madinat Al Mataar · Dubai South Residential District | A G W Real Estate Development L.L.C | Under construction | 30.1% | Feb 2027 3 mo to go | — | 68 |
| Azizi Venice 12821 · Madinat Al Mataar · Dubai World Central | Azizi Developments L.L.C | Under construction | 67.4% | Dec 2025 10 mo past | 10 mo | 66 |
| Lilian Residences3468 · Madinat Al Mataar · Dubai South Residential District | London Gate Real Estate Development L.L.C | Under construction | 4.7% | Apr 2028 17 mo to go | — | 66 |
| Oasis Residences3726 · Madinat Al Mataar · Dubai South Residential District | Al Helal Al Zahaby Real Estate Development L.L.C | Under construction | 35.3% | Jul 2027 8 mo to go | — | 66 |
| Greenway 23121 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Under construction | 34.4% | May 2028 18 mo to go | — | 59 |
| Avion Residence3653 · Madinat Al Mataar · Dubai South Residential District | Sky View Development L.L.C | Under construction | 35.8% | Mar 2027 4 mo to go | — | 52 |
| Divine Elements4142 · Madinat Al Mataar · Dubai South Residential District | Takmeel Real Estate Development L.L.C | Not started | 0% | Dec 2027 13 mo to go | — | 52 |
| Stories By Mirfa4353 · Madinat Al Mataar · Dubai South Residential District | Mirfa Harmony Real Estate Development L.L.C | Under construction | 0.5% | Mar 2028 16 mo to go | — | 51 |
| Expo City Valley2623 · Madinat Al Mataar · Dubai World Central | Expo City Valley Development FZCO | Under construction | 66% | Jan 2026 9 mo past | 9 mo | 50 |
| The Eighty Three3270 · Madinat Al Mataar · Dubai South Residential District | Oksa Developer L.L.C | Under construction | 60% | Dec 2026 1 mo to go | — | 50 |
| The Collective3888 · Madinat Al Mataar · Dubai South Residential District | Bold Living Real Estate Development L.L.C | Under construction | 5.7% | Mar 2028 16 mo to go | — | 49 |
| Expo City Sky Residences2617 · Madinat Al Mataar · Expo City | Expo City Sky Residences Development FZCO | Under construction | 52.7% | — | — | 47 |
| Cresswell Views3583 · Madinat Al Mataar · Dubai South Residential District | ADEV PROPERTIES (Br of ARADY PROPERTIES - PSC )(Dubai Branch ) | Under construction | 60.2% | Dec 2026 1 mo to go | — | 47 |
| Views VII by Golden Woods3233 · Madinat Al Mataar · Dubai South Residential District | Golden Wood Real Estate Development L.L.C | Under construction | 90.4% | Jul 2026 3 mo past | 3 mo | 46 |
| South Bay 5 Premium2985 · Madinat Al Mataar · Dubai South Residential District | Dubai South Properties DWC LLC | Under construction | 77.8% | — | — | 45 |
| South Bay 3 Premium2711 · Madinat Al Mataar · Dubai South Residential District | Dubai South Properties DWC LLC | Under construction | 88.4% | — | — | 43 |
| Livia Residence3687 · Madinat Al Mataar · Dubai South Residential District | Barco Properties Development L.L.C | Under construction | 14.7% | Apr 2027 5 mo to go | — | 43 |
| Waada- Raiha3783 · Madinat Al Mataar · Dubai World Central | Bt Properties DWC LLC | Under construction | 7% | Oct 2028 23 mo to go | — | 42 |
| MIORAH By Zoya4228 · Madinat Al Mataar · Dubai South Residential District | Zoya One Real Estate Developments L.L.C | Under construction | 16.1% | Aug 2027 9 mo to go | — | 39 |
| South Bay 12452 · Madinat Al Mataar · Dubai South Residential District | Dubai South Properties DWC LLC | Under construction | 93.7% | Mar 2025 19 mo past | 19 mo | 38 |
| Timber Terrace4165 · Madinat Al Mataar · Dubai South Residential District | Timber Terrace Development L.L.C | Not started | 0% | Jul 2027 8 mo to go | — | 37 |
| South Bay 22584 · Madinat Al Mataar · Dubai South Residential District | Dubai South Properties DWC LLC | Under construction | 93.8% | May 2026 5 mo past | 5 mo | 35 |
| Lincoln Star Residence3102 · Madinat Al Mataar · Dubai South Residential District | Lincoln Star Real Estate Development L.L.C | Under construction | 47.2% | Sep 2026 1 mo past | 1 mo | 35 |
| Nanma Lotus4447 · Madinat Al Mataar · Dubai South Residential District | Nanma Properties L.L.C | Under construction | 3.6% | Feb 2028 15 mo to go | — | 35 |
| Westar Altair3515 · Madinat Al Mataar · Dubai South Residential District | Westar Properties L.L.C | Under construction | 62.9% | May 2027 6 mo to go | — | 32 |
| South Bay 4 Premium2844 · Madinat Al Mataar · Dubai South Residential District | Dubai South Properties DWC LLC | Under construction | 85.5% | — | — | 31 |
| Bhuvi Residence3541 · Madinat Al Mataar · Dubai South Residential District | Bravima Real Estate Development L.L.C | Under construction | 31.6% | Dec 2026 1 mo to go | — | 31 |
| South Bay 6 Premium3051 · Madinat Al Mataar · Dubai South Residential District | Dubai South Properties DWC LLC | Under construction | 82.1% | — | — | 29 |
| Coventry 663678 · Madinat Al Mataar · Dubai South Residential District | Gfs Wonders Developers L.L.C | Not started | 0% | May 2027 6 mo to go | — | 29 |
| Hayat 74424 · Madinat Al Mataar · Dubai World Central | Dubai South Properties DWC LLC | Not started | 0% | Mar 2029 28 mo to go | — | 29 |
| VOI Residence by HVM Living3234 · Madinat Al Mataar · Dubai South Residential District | Hvm Living Real Estate Development L.L.C | Under construction | 15.6% | Sep 2026 1 mo past | 1 mo | 28 |
| Cresswell Plaza4359 · Madinat Al Mataar · Dubai South Residential District | Essa Bokhowa Properties L.L.C | Under construction | 60.1% | Sep 2026 1 mo past | 1 mo | 27 |
| Altair 523657 · Madinat Al Mataar · Dubai South Residential District | Acube Abodes Real Estate Development L.L.C | Under construction | 10.1% | Dec 2027 13 mo to go | — | 23 |
| Astra Residences4040 · Madinat Al Mataar · Dubai South Residential District | Dugasta Properties Development L.L.C | Under construction | 15.3% | Aug 2027 9 mo to go | — | 23 |
| Bling Avenue 13582 · Madinat Al Mataar · Dubai South Residential District | Bling Development DWC LLC | Under construction | 68.3% | Jul 2026 3 mo past | 3 mo | 21 |
| Golf Lane3111 · Madinat Al Mataar · Dubai World Central | Emaar Dubai South DWC LLC | Under construction | 30.1% | — | — | 19 |
| Elinor4513 · Madinat Al Mataar · Dubai South Residential District | Zoya One Real Estate Developments L.L.C | Pending | 0% | Jun 2028 19 mo to go | — | 16 |
| Sikanta Residences3658 · Madinat Al Mataar · Dubai South Residential District | Sikanta Real Estate Development L.L.C | Under construction | 13.9% | Mar 2027 4 mo to go | — | 15 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
168 phases| DLD end year | Projects | Units |
|---|---|---|
| 2019 | 1 | 108 |
| 2020 | 1 | 209 |
| 2023 | 1 | 80 |
| 2025 | 7 | 2,258 |
| 2026 | 23 | 7,987 |
| 2027 | 40 | 12,638 |
| 2028 | 40 | 6,989 |
| 2029 | 34 | 8,449 |
| 2030 | 9 | 2,322 |
| No end date | 12 | 4,818 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Madinat Al Mataar
Own a unit in one of these projects? Track it free
Area prices
2022-Q1 – 2026-Q4Median AED/sqft of off-plan sales of apartments by quarter in DLD area Madinat Al Mataar, where most of the community’s projects are registered.
| Quarter | DLD area Madinat Al Mataar |
|---|---|
| 2022-Q1 | — |
| 2022-Q2 | — |
| 2022-Q3 | — |
| 2022-Q4 | — |
| 2023-Q1 | — |
| 2023-Q2 | — |
| 2023-Q3 | 1,530 |
| 2023-Q4 | 1,661 |
| 2024-Q1 | 1,734 |
| 2024-Q2 | 1,900 |
| 2024-Q3 | 1,549 |
| 2024-Q4 | 1,637 |
| 2025-Q1 | 1,943 |
| 2025-Q2 | 1,814 |
| 2025-Q3 | 1,575 |
| 2025-Q4 | 1,670 |
| 2026-Q1 | 1,565 |
| 2026-Q2 | 1,699 |
| 2026-Q3 | 1,719 |
| 2026-Q4 | 1,680 |
DLD area Madinat Al Mataar, median AED/sqft of off-plan sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.
Source: Dubai Land Department transactions, on Dubai Data.
Rents in DLD area Madinat Al Mataar
New Ejari rent contracts for apartments across DLD area Madinat Al Mataar, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.
| Bedrooms | Median annual rent | New contracts | Change on a year earlier |
|---|---|---|---|
| Studio | AED 41,000 | 818 | +2.5% |
| 1 BR | AED 56,500 | 1,084 | +0.9% |
| 2 BR | AED 85,000 | 1,080 | 0% |
| 3 BR | AED 120,000 | 182 | 0% |
New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.
Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.
Registered sales in DLD area Madinat Al Mataar
The newest home sales DLD has registered in DLD area Madinat Al Mataar, as DLD publishes them, with the project where DLD names one.
| Date | Project | Market | Type | Size (sqft) | Price (AED) | AED/sqft |
|---|---|---|---|---|---|---|
| 5 November 2026 | South Bay 1 | off-plan | Villa · 5 BR | 4,219 | 4,975,000 | 1,179 |
| 5 November 2026 | Greenview 3 | ready | Villa · 4 BR | 2,486 | 3,150,000 | 1,267 |
| 5 November 2026 | Greenview 3 | ready | Villa · 3 BR | 1,483 | 2,675,000 | 1,804 |
| 5 November 2026 | Expo Valley Views | off-plan | Apartment · 2 BR | 1,360 | 2,673,000 | 1,965 |
| 5 November 2026 | Expo Valley Views | off-plan | Apartment · 2 BR | 1,338 | 2,563,000 | 1,916 |
| 5 November 2026 | Terra Woods | off-plan | Apartment · 2 BR | 1,113 | 2,472,888 | 2,222 |
| 5 November 2026 | Expo Valley Views | off-plan | Apartment · 1 BR | 890 | 1,701,000 | 1,911 |
| 5 November 2026 | Terra Woods | off-plan | Apartment · 1 BR | 745 | 1,628,888 | 2,186 |
| 5 November 2026 | The Harmony | off-plan | Apartment · 2 BR | 1,237 | 1,564,466 | 1,265 |
| 5 November 2026 | Marquis Horizon | off-plan | Apartment · 2 BR | 1,105 | 1,480,464 | 1,340 |
The newest 10 of 16,203 registered sales in the 12 months to 5 November 2026
Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
Places inside the community
Places inside the Dubai Municipality outline of the community, by kind.
Metro and tram stations: Roads and Transport Authority (RTA) via Dubai Data. Other places: © OpenStreetMap contributors.
Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026; Dubai Municipality community outlines. Methodology