Emaar Dubai South DWC LLC إعمار دبي الجنوب دي دبليو سي ش.ذ.م.م 35 projects in the DLD register: 12 completed, 16 under construction, 7 not started or pending. 0 of the 13 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 35- Median time from start to completion: 34 months (12 completed projects).
- 3,201 units and villas in completed projects; 5,540 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 12 completed projects with both dates. In 10 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 0 of 13 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Emaar Dubai South DWC LLC Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Greenspoint 23558 · Madinat Al Mataar · Dubai World Central | Under construction | 40.1% | Mar 2029 28 mo to go | 244 | 245 |
| Golf Vale4416 · Madinat Al Mataar · Dubai World Central | Not started | 0% | Mar 2030 40 mo to go | 262 | 238 |
| Greenspoint3514 · Madinat Al Mataar · Dubai World Central | Under construction | 42.9% | Mar 2029 28 mo to go | 196 | 197 |
| Golf Meadow3579 · Madinat Al Mataar · Dubai World Central | Under construction | 4.5% | Jul 2029 32 mo to go | 188 | 183 |
| Greenridge3283 · Madinat Al Mataar · Dubai World Central | Under construction | 35.6% | Dec 2028 25 mo to go | 520 | 182 |
| Golf Dale3427 · Madinat Al Mataar · Dubai World Central | Not started | 0.3% | Dec 2028 25 mo to go | 200 | 182 |
| Golf Hills 24119 · Madinat Al Mataar · Dubai World Central | Under construction | 4.2% | Sep 2029 34 mo to go | 204 | 181 |
| Golf Fields4415 · Madinat Al Mataar · Dubai World Central | Not started | 0% | Feb 2030 39 mo to go | 181 | 181 |
| Golf Hills4117 · Madinat Al Mataar · Dubai World Central | Under construction | 3.7% | Sep 2029 34 mo to go | 204 | 178 |
| Golf Verge3578 · Madinat Al Mataar · Dubai World Central | Under construction | 4.2% | May 2029 30 mo to go | 204 | 177 |
| Golf Edge3385 · Madinat Al Mataar · Dubai World Central | Not started | 0% | Feb 2029 27 mo to go | 179 | 168 |
| Vista Ridge4201 · Madinat Al Mataar · Dubai World Central | Not started | 0% | Sep 2029 34 mo to go | 198 | 161 |
| Grove Ridge4200 · Madinat Al Mataar · Dubai World Central | Not started | 0% | Sep 2029 34 mo to go | 193 | 160 |
| Greenville 23319 · Madinat Al Mataar · Dubai World Central | Under construction | 47.3% | Mar 2029 28 mo to go | 148 | 150 |
| Greenville3316 · Madinat Al Mataar · Dubai World Central | Under construction | 46% | Mar 2029 28 mo to go | 140 | 140 |
| Golf Acres3426 · Madinat Al Mataar · Dubai World Central | Under construction | 3.5% | Dec 2028 25 mo to go | 158 | 113 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 23, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.