Emaar Development P.J.S.C. إعمار للتطوير (مساهمة عامة) 110 projects in the DLD register: 58 completed, 44 under construction, 8 not started or pending. 0 of the 41 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 110- Median time from start to completion: 40 months (58 completed projects).
- 22,947 units and villas in completed projects; 12,652 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 57 completed projects with both dates. In 38 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 0 of 41 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Emaar Development P.J.S.C. Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| The Valley - Vindera3175 · Al Yufrah 1 | Under construction | 2% | Dec 2028 25 mo to go | 745 | 578 |
| Grand Polo - Equiterra4185 · Dubai Investment Park Second | Under construction | 0.8% | Aug 2029 33 mo to go | 547 | 510 |
| The Valley - Farm Grove3430 · Al Yufrah 1 · The Valley | Under construction | 10% | Dec 2028 25 mo to go | 482 | 499 |
| The Valley - Rivera3174 · Al Yufrah 1 · The Valley | Under construction | 3.9% | Nov 2028 24 mo to go | 378 | 385 |
| Grand Polo - Equiterra 24162 · Dubai Investment Park Second | Under construction | 1% | Jul 2029 32 mo to go | 384 | 380 |
| The St. Regis Residences, Downtown Dubai1816 · Burj Khalifa · DownTown Dubai | Under construction | 76.1% | Dec 2026 1 mo to go | 1,108 | 369 |
| The Valley - Velora 23161 · Al Yufrah 1 · The Valley | Under construction | 40.3% | Jul 2028 20 mo to go | 312 | 322 |
| Grand Polo - Equestra4186 · Dubai Investment Park Second | Under construction | 1% | Aug 2029 33 mo to go | 361 | 309 |
| The Valley - Farm Grove 23431 · Al Yufrah 1 · The Valley | Under construction | 9.8% | Oct 2028 23 mo to go | 290 | 300 |
| Downtown Views II1849 · Zaabeel Second | Completed | 100% | Aug 2022 Completed | 1,515 | 259 |
| The Valley - Elva3462 · Al Yufrah 1 · The Valley | Under construction | 25.9% | Oct 2028 23 mo to go | 244 | 254 |
| Marina Cove3328 · Marsa Dubai · Dubai Marina | Under construction | 5.7% | Sep 2029 34 mo to go | 227 | 228 |
| THE BRISTOL Emaar Beachfront3439 · Marsa Dubai · Dubai Harbour | Under construction | 5.8% | Sep 2029 34 mo to go | 229 | 227 |
| Grande2053 · Burj Khalifa · DownTown Dubai | Completed | 100% | Jun 2022 Completed | 906 | 210 |
| Forte1660 · Burj Khalifa · DownTown Dubai | Completed | 100% | Nov 2022 Completed | 927 | 194 |
| The Valley - Avena3158 · Al Yufrah 1 · The Valley | Under construction | 24.5% | Jun 2028 19 mo to go | 322 | 190 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 52, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.