Emaar Properties (P.J.S.C) اعمار العقارية (ش . م. ع) 61 projects in the DLD register: 53 completed, 7 under construction, 1 not started or pending. 0 of the 4 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 61- Median time from start to completion: 36 months (51 completed projects).
- 13,771 units and villas in completed projects; 447 in projects not yet completed.
- Completed a month or more after their DLD end date: 8 of 52 completed projects with both dates. In 41 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 0 of 4 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Emaar Properties (P.J.S.C) Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Burj Khalifa Towers1462 · Burj Khalifa · DownTown Dubai | Completed | 100% | Jan 2012 Completed | 1,078 | 248 |
| 29 Boulevard1276 · Burj Khalifa · DownTown Dubai | Completed | 100% | Apr 2013 Completed | 750 | 169 |
| Park Islands1458 · Marsa Dubai · Dubai Marina | Completed | 100% | Mar 2010 Completed | 734 | 146 |
| Burj Views1451 · Burj Khalifa · DownTown Dubai | Completed | 100% | Sep 2009 Completed | 737 | 140 |
| Dubai Marina Mall1460 · Marsa Dubai · Dubai Marina | Completed | 100% | Dec 2009 Completed | 452 | 104 |
| Golf Heights2469 · Al Thanyah Third · The Greens | Completed | 100% | Jun 2026 Completed | 281 | 97 |
| Marina Shores2425 · Marsa Dubai · Dubai Marina | Under construction | 87.2% | Dec 2026 1 mo to go | 447 | 95 |
| The Dubai Mall1461 · Burj Khalifa · DownTown Dubai | Completed | 100% | Aug 2008 Completed | 456 | 92 |
| Dd Stand Point1277 · Burj Khalifa · DownTown Dubai | Completed | 100% | Dec 2012 Completed | 537 | 92 |
| Emirates Living - Springs 111050 · Al Thanayah Fourth · Emirates Living | Completed | 100% | May 2008 Completed | 484 | 85 |
| Emirates Living - Springs 151053 · Al Thanayah Fourth · Emirates Living | Completed | 100% | Oct 2004 Completed | 478 | 80 |
| Dd Boulevard Central1274 · Burj Khalifa · DownTown Dubai | Completed | 100% | Aug 2012 Completed | 424 | 79 |
| Emirates Living - Springs 31033 · Al Thanayah Fourth · Emirates Living | Completed | 100% | Jan 2004 Completed | 450 | 74 |
| Emirates Living - Springs 141052 · Al Thanayah Fourth · Emirates Living | Completed | 100% | Oct 2004 Completed | 408 | 71 |
| Marina Quays1456 · Marsa Dubai · Dubai Marina | Completed | 100% | Jan 2010 Completed | 450 | 63 |
| Emirates Living - Springs 21032 · Al Thanayah Fourth · Emirates Living | Completed | 100% | Feb 2005 Completed | 484 | 61 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 8, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.