Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 1456Completed450 units

Marina Quays أرصفة مارينا Marsa Dubai · Dubai Marina by Emaar Properties (P.J.S.C)All phases of Dubai Marina Completed 1 January 2010 (DLD) DLD end date Jan 2010 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Dubai Marina towers and the waterfront on a clear day
Area photo: Dubai Marina, not this project
Completed
Jan 2010
DLD end date Jan 2010
Build time
46 months
Mar 2006 → Jan 2010
Latest sales
2,189 AED/sqft
9 sales
1 BR rent
94,500 AED/yr
Gross yield 6.1% · 83 leases
Developer
61 projects
53 completed · 13,771 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3).

DLD has no site-inspection readings for this project in our copy.

Every DLD inspection and every change in the register %, newest first
Date % built Source
5 August 2022 100% DLD register, archived export

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024.

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
46 monthsActual build
46 months
Start date
1 March 2006
DLD end date
1 January 2010
Completion date
1 January 2010
Completion vs DLD end date
On the date

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

Building permits

7 of 7 buildings

Buildings on the project’s plots: 7, on construction permits: 1, as Dubai Municipality lists them.

Furthest stage reached: Completed.

Work not started
Site works
Foundations
Structure
Masonry
Finishes
Final works
Completed
Buildings
7
1 on construction permits
Permit status
Closed
132613
Issued
7 April 2008
Work start
29 March 2006
Completion
23 August 2012
Consultant · contractor
ARIF & BINTOAK CONSULTING ENGINEERS AND ARCHITECTS · AL BASTI & MUKTHA (L.L.C)
Buildings by the furthest work stage Dubai Municipality lists
Work stage Buildings
Completed7

Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.

DLD registration

DLD services ↗
DLD project number
1456
Zoning authority
Dubai Municipality
Master project
Dubai Marina
DLD area
Marsa Dubai
Units · villas
450 · 0
Start → DLD end
Mar 2006 → Jan 2010
Registered unitsStudio 2 · 1 bed 217 · 2 bed 170 · 3 bed 60; sizes 791–1,561 sqft

Also registered: other units 1.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: MARINA QUAYS

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

No off-plan sales are registered for this project since 2020, so there is no launch price.

Prices are over apartments, the type most sales in this project are.

Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest ready sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
1 BR 35 1,896 (5) May 2026 – Nov 2026
2 BR 15 2,269 (5) Nov 2025 – Nov 2026
3 BR 13 3,088 (5) Nov 2025 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Skyline Index

Buildings with sales: 6

Registered sale prices, rents and yields for Marina Quays, from DLD records.

Marina Quays: registered prices and rents on Skyline Index ↗

Median AED/sqft by quarter

2020-Q1 → 2026-Q3

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Marsa Dubai, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents and gross yield

New Ejari rent contracts for apartments in this project, 12 months to 5 November 2026, against the 12 months before. Gross yield: the median annual rent over the median registered ready sale price of the same bedroom count in this project over the same 12 months.

Bedrooms Median annual rent New contracts Change on a year earlier Gross yield
1 BR AED 94,500 83 -10% 6.1%
2 BR AED 150,000 35 -9.1% —
3 BR AED 300,000 8 -11.8% —

Gross yield is before service charges, other costs and empty months.

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 18; registered amount AED 33.7M.

Since the first registration in 2009-Q4: 481 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Service charges

What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.

Apartment buildings’ budgets; villa and townhouse budgets are left out.
18.61 AED/sqft a year
Dubai Marina: median of 73 developments’ owners’ association budgets, 2026

Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.

Source: Dubai Land Department, owners’ association budgets (service charges).

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 26 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
1 September 2026readyApartment · 1 BR 775 1,450,000 1,871
31 August 2026readyApartment · 2 BR 1,256 2,850,000 2,269
4 August 2026readyApartment · 1 BR 791 1,500,000 1,896
3 August 2026readyApartment · 1 BR 791 1,550,000 1,960
31 July 2026readyApartment · 1 BR 762 3,339 4
23 July 2026readyApartment · 1 BR 762 16,588 22
21 July 2026readyApartment · 2 BR 1,256 2,850,000 2,269
9 July 2026readyApartment · 1 BR 983 1,850,000 1,882
16 June 2026readyApartment · 1 BR 788 1,725,000 2,189
13 May 2026readyApartment · 2 BR 1,567 4,000,000 2,553

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationMarsa Dubai · Dubai Municipality community

freshmart · 160 mSupermarket · 180 mCarrefour · 200 mDubai Marina Mall · 340 mJumeirah Beach Residence 1 · 370 mPark · 460 mDubai Marina Mall · 520 mMarina Beach Dubai · 660 mDMCC Metro Station · 670 mPark · 700 mJumeirah Lakes Towers Park · 920 mEmirates Hospital · 1.1 kmDAMAC Properties Metro Station · 1.1 kmHealth Avenue Polyclinics · 1.2 kmBluewaters Wharf Retail · 1.3 kmYacht Rental Dubai Marina · 1.3 kmThe Wharf · 1.4 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Metro and tram Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationDMCC Metro Station · Red Metro line · 670 m
Tram stopJumeirah Beach Residence 1 · Tram line · 370 m
MallDubai Marina Mall · 340 m
Supermarketfreshmart · 160 m
HospitalEmirates Hospital · 1.1 km
SchoolEmirates International School - Meadows · 2.3 km
ParkPark · 460 m
BeachMarina Beach Dubai · 660 m

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 28, with 11,957 units and villas.

2023: 9262025: 4072026: 3,2772027: 2,2992028: 1,6492029: 6892030: 813No end date: 1,897

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Marsa Dubai: 27

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Franck muller Vanguard 48.3% Nov 2027 2,454 752
Rove Home Dubai Marina 7.8% Mar 2028 3,603 665
W Residences at Dubai Harbour 4% Dec 2028 4,769 337
PELaGOS By IGO 84.2% Mar 2026 2,895 269
Marina Cove 5.7% Sep 2029 2,331 228
THE BRISTOL Emaar Beachfront 5.8% Sep 2029 — 227
Aeternitas Tower 57.9% Dec 2027 2,322 189
Sobha Seahaven Tower B & C 40.2% Oct 2028 4,100 162
Dubai Harbour Residences (Area 1) 30.3% Jan 2028 4,658 161
Damac Bay 33.8% Jan 2027 3,317 142
Seapoint 36.8% Mar 2028 4,921 138
Damac Bay 2 30.3% — 4,319 137

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Marsa Dubai

Developer in DLD data Emaar Properties (P.J.S.C) · DLD developer no. 555

Projects registered
61
53 completed · 7 under construction · 1 not started
Units delivered
13,771
447 in the pipeline
Median build time
36 months
completed projects measured: 51
Past the DLD end date
0
of 4 under construction with a DLD end date

Completed a month or more after their DLD end date: 8 of 52 completed projects with both dates. In 41 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Emaar Properties (P.J.S.C) is one of 7 DLD-registered developers we list together as Emaar. See the group

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Dubai Marina

DLD lists 67 projects in the master project Dubai Marina.

Pier 8Under construction · 70.1% · Mar 2026
PELaGOS By IGOUnder construction · 84.2% · Mar 2026
Liv LuxUnder construction · 87.1% · Dec 2026
Marina ShoresUnder construction · 87.2% · Dec 2026
Aeternitas TowerUnder construction · 57.9% · Dec 2027
Rove Home Dubai MarinaUnder construction · 7.8% · Mar 2028
Marina CoveUnder construction · 5.7% · Sep 2029
Aba Lux LivingUnder construction · 6.9% · —
Six Senses Residences Dubai MarinaUnder construction · 26.7% · —
Mada'inNot started · 0% · Feb 2028
Alseef ICompleted · 100% · Apr 2005

Questions about Marina Quays

When was Marina Quays completed?

Marina Quays is recorded as completed on 1 January 2010 (DLD register of 1 November 2026).

Who is the developer of Marina Quays?

Emaar Properties (P.J.S.C), as registered with DLD.

What is the DLD project number of Marina Quays?

1456.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error