DLD project no. 3233Under construction68 units
Views VII by Golden Woods لجولدن وودس VII فيوز 90.4% built (DLD register as of 1 November 2026) · DLD end date Jul 2026 · past its DLD end date by 3 months DLD register as of 1 November 2026. DLD still lists the project as under construction.
CompletionDLD readings of % built, beside the share of the planned period gone
% built and period elapsed
1 November 2026Two separate measures: one is DLD's % built, the other is time on the calendar.
| Date | % built | Source |
|---|---|---|
| 8 May 2026 | 90.4% | DLD inspection |
| 3 December 2025 | 64.5% | DLD inspection |
| 22 August 2024 | 0% | DLD inspection |
Source: Dubai Land Department projects register, as of 1 November 2026. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗ Period elapsed: our calculation from DLD’s start and end dates.
Our completion calculation
Pace since the last two DLD readings: —
Our calculation from DLD readings. It describes the recent pace only; it is not a forecast of the completion date.
Site timeline
± 6 monthsEach date is ± 6 months. This is our reading, not DLD's; no image is shown. Read from imagery dated 22 November 2021 to 15 March 2025; method imagery-v1.
Changes in the DLD register
Source: DLD projects register exports, compared by CraneScore. Dates and progress are those in the Dubai Land Department projects register on each register date, not inspection dates. DLD can revise the end date; we keep every register reading from 28 October 2026 on and list the changes here.
Inspection photos and reports
DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.
CraneScore links to DLD and does not copy or host its photos or reports.
DLD registration
DLD services ↗Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: Residential Building (G+4+ROOF)
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
Dubai Statistics Center residential price index (flats), 2024-Q4 to 2026-Q2: +5.5%.
Prices are over apartments, the type most sales in this project are.
| Bedrooms | Sales, 24 months | Latest median AED/sqft | Latest sales |
|---|---|---|---|
| Studio | 20 | — | — |
| 2 BR | 20 | 1,300 (7) | Nov 2025 – Nov 2026 |
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Median AED/sqft by quarter
2024-Q4 → 2026-Q4| Quarter | Registered sales | Median AED/sqft | DLD area Madinat Al Mataar |
|---|---|---|---|
| 2024-Q4 | 1 (off-plan 1, ready 0) | — | 1,637 |
| 2025-Q1 | 14 (off-plan 14, ready 0) | 1,298 | 1,943 |
| 2025-Q2 | 6 (off-plan 6, ready 0) | 1,021 | 1,814 |
| 2025-Q3 | 10 (off-plan 10, ready 0) | 1,000 | 1,575 |
| 2025-Q4 | 3 (off-plan 3, ready 0) | — | 1,670 |
| 2026-Q1 | 7 (off-plan 7, ready 0) | 1,300 | 1,565 |
| 2026-Q2 | 3 (off-plan 3, ready 0) | — | 1,699 |
| 2026-Q3 | 1 (off-plan 1, ready 0) | — | 1,719 |
| 2026-Q4 | 1 (off-plan 1, ready 0) | — | 1,680 |
Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Madinat Al Mataar, median AED/sqft of off-plan sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.
Registered sales per quarter
| Quarter | Registered sales | Median AED/sqft | DLD area Madinat Al Mataar |
|---|---|---|---|
| 2024-Q4 | 1 (off-plan 1, ready 0) | — | 1,637 |
| 2025-Q1 | 14 (off-plan 14, ready 0) | 1,298 | 1,943 |
| 2025-Q2 | 6 (off-plan 6, ready 0) | 1,021 | 1,814 |
| 2025-Q3 | 10 (off-plan 10, ready 0) | 1,000 | 1,575 |
| 2025-Q4 | 3 (off-plan 3, ready 0) | — | 1,670 |
| 2026-Q1 | 7 (off-plan 7, ready 0) | 1,300 | 1,565 |
| 2026-Q2 | 3 (off-plan 3, ready 0) | — | 1,699 |
| 2026-Q3 | 1 (off-plan 1, ready 0) | — | 1,719 |
| 2026-Q4 | 1 (off-plan 1, ready 0) | — | 1,680 |
Registered sales per quarter, off-plan and ready units. Source: DLD.
Rents in DLD area Madinat Al Mataar
New Ejari rent contracts for apartments across DLD area Madinat Al Mataar, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.
| Bedrooms | Median annual rent | New contracts | Change on a year earlier |
|---|---|---|---|
| Studio | AED 41,000 | 818 | +2.5% |
| 1 BR | AED 56,500 | 1,084 | +0.9% |
| 2 BR | AED 85,000 | 1,080 | 0% |
| 3 BR | AED 120,000 | 182 | 0% |
New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.
Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.
Registered sales
The newest sales DLD has registered in this project, as DLD publishes them.
| Date | Market | Type | Size (sqft) | Price (AED) | AED/sqft |
|---|---|---|---|---|---|
| 27 October 2026 | off-plan | Apartment · 1 BR | 791 | 1,266,176 | 1,601 |
| 15 September 2026 | off-plan | Apartment · 3 BR | 1,768 | 2,165,898 | 1,225 |
| 6 May 2026 | off-plan | Apartment · 2 BR | 1,021 | 1,224,636 | 1,199 |
| 6 May 2026 | off-plan | Apartment · 2 BR | 1,021 | 1,224,636 | 1,199 |
| 6 April 2026 | off-plan | Apartment · Studio | 406 | 430,000 | 1,059 |
| 4 March 2026 | off-plan | Apartment · 2 BR | 970 | 1,248,583 | 1,287 |
| 4 March 2026 | off-plan | Apartment · Studio | 337 | 471,674 | 1,400 |
| 17 February 2026 | off-plan | Apartment · 2 BR | 970 | 1,261,052 | 1,300 |
| 28 January 2026 | off-plan | Apartment · 2 BR | 970 | 1,261,052 | 1,300 |
| 5 January 2026 | off-plan | Apartment · 2 BR | 964 | 1,253,083 | 1,300 |
Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
Looking for a unit in this or similar projects?
Tell us what you are looking for in Views VII by Golden Woods or similar projects. We reply by e-mail, and your request stays with CraneScore.
Estimated value range
| Bedrooms | Range, AED | Based on | Compared at |
|---|---|---|---|
| 2 BR | 1,210,000 – 1,220,000 | 7 sales, 12 months | This project |
Estimate as of 5 November 2026 Track this unit
Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.
Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Jul 2026); move it with the slider.
A scenario from your own inputs, not this project's verified payment plan.
Common plans
Plan shares add up to 100% (must be 100%).
Payments per quarter
AED| Quarter | Paid |
|---|---|
| 2026-Q4 | AED 1,045,000 · AED 1,045,000 paid so far |
Payments per quarter, AED, fees included. Illustration from your inputs.
The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.
Mortgage for a unit here
Questions about financing a unit in Views VII by Golden Woods? Leave your details and we reply by e-mail. Your request stays with CraneScore.
LocationMadinat Al Mataar · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 74, with 7,057 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2019 | 1 | 108 |
| 2025 | 1 | 113 |
| 2026 | 13 | 782 |
| 2027 | 24 | 1,174 |
| 2028 | 24 | 2,596 |
| 2029 | 9 | 1,994 |
| 2030 | 1 | 290 |
| No end date | 1 | 0 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Madinat Al Mataar: 167
Open projects in the same DLD area with a DLD end year from 2025 to 2027, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Azizi Venice 14 | 30.3% | May 2026 | 1,649 | 2,546 |
| Azizi Venice 6 | 11.6% | Dec 2027 | 2,032 | 1,302 |
| Azizi Venice 7 | 29.2% | Jan 2026 | 1,849 | 1,180 |
| Azizi Venice 15 | 0% | May 2027 | 1,715 | 904 |
| azizi venice 13 | 45.9% | Sep 2027 | 1,675 | 797 |
| azizi venice 12 | 21.6% | Sep 2027 | 1,685 | 753 |
| Azizi Venice 11 | 25.9% | Aug 2027 | 1,667 | 696 |
| Azizi Venice 16 | 0% | Jun 2027 | 1,898 | 310 |
| Azizi Venice 5 | 63.5% | Oct 2025 | 1,659 | 309 |
| Expo City Al Waha Residences 01 | 65.8% | Jun 2027 | 2,515 | 286 |
| Expo City Al Waha Residences 02 | 61.4% | Jun 2027 | 2,550 | 273 |
| Azizi Venice 2 | 57.2% | Dec 2025 | — | 264 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Golden Wood Real Estate Development L.L.C · DLD developer no. 1201
Completed a month or more after their DLD end date: 0 of 2 completed projects with both dates. In 2 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Other projects in Dubai South Residential District
DLD lists 119 projects in the master project Dubai South Residential District.
Questions about Views VII by Golden Woods
When is Views VII by Golden Woods's handover?
DLD lists an end date of Jul 2026 (register of 1 November 2026); the SPA sets the handover terms.
Is Views VII by Golden Woods past its DLD end date?
Yes. Its DLD end date is Jul 2026, 3 months before the register of 1 November 2026.
How far along is Views VII by Golden Woods?
90.4% built in the DLD register of 1 November 2026.
Who is the developer of Views VII by Golden Woods?
Golden Wood Real Estate Development L.L.C, as registered with DLD.
What is the DLD project number of Views VII by Golden Woods?
3233.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error