Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026
| Project | Developer | DLD status | Built | DLD end date | Past DLD end date | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Samana Waves2345 · Al Barsha South Fourth · Jumeirah Village Circle | Samana Si Holding Limited Dubai Branch | Under construction | 90.6% | Apr 2026 6 mo past | 6 mo | 41 |
| Samana Waves 22574 · Al Barsha South Fourth · Jumeirah Village Circle | Samana Si Holding Limited Dubai Branch | Under construction | 52.1% | Mar 2026 7 mo past | 7 mo | 17 |
| Miami By Sd2454 · Al Barsha South Fifth · Jumeirah Village Triangle | Samana Si Holding Limited Dubai Branch | Under construction | 71.3% | Jul 2026 3 mo past | 3 mo | 10 |
How to read this list
- DLD status
- Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
- Built
- The latest % complete that DLD publishes for the project.
- DLD end date
- The completion date in the DLD register, with whole months to go from the export date.
- Past DLD end date
- Whole months since the DLD end date, for projects DLD still lists as under construction.
- Sales, 24 mo
- Sales of units in the project registered with DLD in the last 24 months.