Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026
| Project | Developer | DLD status | Built | DLD end date | Sales, 24 mo |
|---|---|---|---|---|---|
| Ocean Pearl 2 By SD3238 · Palm Deira | Samana Star Real Estate Development L.L.C | Under construction | 23.3% | Mar 2027 4 mo to go | 76 |
| Rome 3 by SD3459 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Samana Star Real Estate Development L.L.C | Under construction | 10.2% | Jun 2028 19 mo to go | 65 |
| Ocean Pearl By SD3167 · Palm Deira | Samana Star Real Estate Development L.L.C | Under construction | 25.1% | Dec 2026 1 mo to go | 56 |
| Manhattan 2 by SD2802 · Al Barsha South Fourth · Jumeirah Village Circle | Samana Star Real Estate Development L.L.C | Under construction | 21.2% | Nov 2026 under 1 mo past | 43 |
| Manhattan 1 by SD2794 · Al Barsha South Fourth · Jumeirah Village Circle | Samana Star Real Estate Development L.L.C | Under construction | 30.3% | — | 41 |
| Rome 2 by SD3329 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Samana Star Real Estate Development L.L.C | Under construction | 32.9% | Jun 2027 7 mo to go | 40 |
| Rome by SD3218 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Samana Star Real Estate Development L.L.C | Under construction | 38.7% | Dec 2027 13 mo to go | 33 |
| California 2 by SD2883 · Jabal Ali First · Discovery Gardens | Samana Star Real Estate Development L.L.C | Under construction | 33.7% | Oct 2026 under 1 mo past | 30 |
How to read this list
- DLD status
- Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
- Built
- The latest % complete that DLD publishes for the project.
- DLD end date
- The completion date in the DLD register, with whole months to go from the export date.
- Past DLD end date
- Whole months since the DLD end date, for projects DLD still lists as under construction.
- Sales, 24 mo
- Sales of units in the project registered with DLD in the last 24 months.