Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026
| Project | Developer | DLD status | Built | DLD end date | Sales, 24 mo |
|---|---|---|---|---|---|
| Waada - Altura 24085 · Madinat Al Mataar · Dubai World Central | Bt Properties DWC LLC | Under construction | 7.2% | Mar 2029 28 mo to go | 237 |
| Waada - Altura 14163 · Madinat Al Mataar · Dubai World Central | Bt Properties DWC LLC | Under construction | 1.9% | Apr 2029 29 mo to go | 222 |
| Waada - Cascada 13731 · Madinat Al Mataar · Dubai World Central | Bt Properties DWC LLC | Under construction | 1.6% | Oct 2028 23 mo to go | 178 |
| Waada - Rayhan 13730 · Madinat Al Mataar · Dubai World Central | Bt Properties DWC LLC | Under construction | 15.1% | Oct 2028 23 mo to go | 144 |
| Waada - Cascada 23732 · Madinat Al Mataar · Dubai World Central | Bt Properties DWC LLC | Not started | 0% | Mar 2029 28 mo to go | 84 |
| Waada- Raiha3783 · Madinat Al Mataar · Dubai World Central | Bt Properties DWC LLC | Under construction | 7% | Oct 2028 23 mo to go | 42 |
How to read this list
- DLD status
- Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
- Built
- The latest % complete that DLD publishes for the project.
- DLD end date
- The completion date in the DLD register, with whole months to go from the export date.
- Past DLD end date
- Whole months since the DLD end date, for projects DLD still lists as under construction.
- Sales, 24 mo
- Sales of units in the project registered with DLD in the last 24 months.