DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026

1–8 of 8 projects, most registered sales in 24 months first

1–8 of 8 projects, most registered sales in 24 months first
Project Developer DLD status Built DLD end date Past DLD end date Sales, 24 mo
Damac Lagoons - Portofino2356 · Al Hebiah Fifth · DAMAC LagoonsIsland Oasis Properties Under construction 97.1% Jun 2025 16 mo past16 mo 267
Damac Lagoons - Ibiza2486 · Al Hebiah FifthIsland Oasis Properties Under construction 78.9% Dec 2025 10 mo past10 mo 254
Damac Lagoons - Mykonos2487 · Al Hebiah Fifth · DAMAC LagoonsIsland Oasis Properties Under construction 81.1% Dec 2025 10 mo past10 mo 219
Damac Lagoons - Nice 12335 · Al Hebiah Fifth · DAMAC LagoonsIsland Oasis Properties Under construction 93.7% Jul 2025 15 mo past15 mo 171
Damac Lagoons - Marbella2489 · Al Hebiah FifthIsland Oasis Properties Under construction 87.3% Dec 2025 10 mo past10 mo 168
Damac Lagoons - Monte Carlo2488 · Al Hebiah FifthIsland Oasis Properties Under construction 86.4% Dec 2025 10 mo past10 mo 149
Damac Lagoons - Venice (1)2396 · Al Hebiah Fifth · DAMAC LagoonsIsland Oasis Properties Under construction 74.4% Sep 2025 13 mo past13 mo 131
Damac Lagoons - Nice 22336 · Al Hebiah Fifth · DAMAC LagoonsIsland Oasis Properties Under construction 83.9% Jul 2025 15 mo past15 mo 107

How to read this list

DLD status
Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
Built
The latest % complete that DLD publishes for the project.
DLD end date
The completion date in the DLD register, with whole months to go from the export date.
Past DLD end date
Whole months since the DLD end date, for projects DLD still lists as under construction.
Sales, 24 mo
Sales of units in the project registered with DLD in the last 24 months.