Al Aryam Phase One L.L.C الاريام المرحلة الاولى ش.ذ.م.م 5 projects in the DLD register: 5 completed, 0 under construction, 0 not started or pending. DLD projects register, export of 1 November 2026
Projects
5
in the DLD register
Completed
5
1,898 units delivered
Not yet completed
0
0 units in the pipeline
Delivery record
Projects: 5Completed 5
- Median time from start to completion: 32 months (5 completed projects).
- 1,898 units and villas in completed projects; 0 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 5 completed projects with both dates. In 4 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Al Aryam Phase One L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| REEM-MIRA Community Ph 41825 · Al Yelayiss 1 · Al Aryam | Completed | 100% | Jul 2016 Completed | 516 | 63 |
| REEM-MIRA Community Ph 31824 · Al Yelayiss 1 · Al Aryam | Completed | 100% | Jul 2016 Completed | 402 | 60 |
| REEM-MIRA Community Ph 21793 · Al Yelayiss 1 · Al Aryam | Completed | 100% | Aug 2016 Completed | 334 | 44 |
| REEM-MIRA Community PH51342 · Al Yelayiss 1 | Completed | 100% | Sep 2016 Completed | 316 | 34 |
| REEM-MIRA Community Ph 11792 · Al Yelayiss 1 · Al Aryam | Completed | 100% | Aug 2016 Completed | 330 | 33 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.