Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 1342Completed316 units

REEM-MIRA Community PH5 مجتمع ريم ميرا PH5 Al Yelayiss 1 by Al Aryam Phase One L.L.C Completed 30 September 2016 (DLD) DLD end date Oct 2016 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Sep 2016
DLD end date Oct 2016
Build time
34 months
Dec 2013 → Sep 2016
Latest sales
1,299 AED/sqft
7 sales
3 BR rent
164,558 AED/yr
26 leases, 12 months
Developer
5 projects
5 completed · 1,898 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3). Latest DLD inspection: 100% built on 16 March 2017 (inspections: 9).
Every DLD inspection and every change in the register %, newest first
Date % built Source
16 March 2017 100% DLD inspection
15 December 2016 99.2% DLD inspection
19 October 2016 98.3% DLD inspection
17 August 2016 96.2% DLD inspection
25 May 2016 95.7% DLD inspection
4 October 2015 62.7% DLD inspection
2 June 2015 45.3% DLD inspection
25 December 2014 26.8% DLD inspection
6 October 2013 0% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
34 monthsActual build
34 months
Start date
1 December 2013
DLD end date
6 October 2016
Completion date
30 September 2016
Completion vs DLD end date
On the date

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

Building permits

1 of 1 buildings

Buildings on the project’s plots: 1, on construction permits: 1, as Dubai Municipality lists them.

Furthest stage reached: Finishes.

Work not started
Site works
Foundations
Structure
Masonry
Finishes
Final works
Completed
Buildings
1
1 on construction permits
Permit status
Closed
269146
Issued
31 January 2016
Work start
31 January 2016
Completion
21 March 2017
Consultant · contractor
EGIS ENGINEERING CONSULTANTS L.L.C S.O.C · AL AHMADIAH CONTRACTING & TRADING
Buildings by the furthest work stage Dubai Municipality lists
Work stage Buildings
Finishes1

Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.

DLD registration

DLD services ↗
DLD project number
1342
Escrow agent
Dubai Islamic Bank (Public Joint Stock Company)
Zoning authority
Dubai Development Authority (DDA)
DLD area
Al Yelayiss 1
Units · villas
0 · 316
Start → DLD end
Dec 2013 → Oct 2016
Registered units3 bed 176 · 4 bed 140; sizes 2,507–2,559 sqft

Homes: villas 316.

Also registered: shops and showrooms 8.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Mira 5 - 316 Freehold G+1 attached villas located in Al Yelayiss 1 Community.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

No off-plan sales are registered for this project since 2020, so there is no launch price.

Prices are over villas and townhouses, the type most sales in this project are.

Registered sales of villas and townhouses by bedroom count over the last 24 months, and the median AED/sqft of the latest ready sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
3 BR 19 1,433 (5) Nov 2025 – Nov 2026
4 BR 14 1,251 (5) May 2026 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2020-Q1 → 2026-Q4

Median AED/sqft of registered sales per quarter (villas and townhouses). Source: DLD. Grey dashed line: DLD area Al Yelayiss 1, median AED/sqft of ready sales of villas and townhouses by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents and gross yield

New Ejari rent contracts for villas and townhouses in this project, 12 months to 5 November 2026, against the 12 months before. Fewer than 10 ready sales per bedroom count in those 12 months, so no yield is shown.

Bedrooms Median annual rent New contracts Change on a year earlier
3 BR AED 164,558 26 -0.3%
4 BR AED 200,000 19 -4.8%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 23; registered amount AED 54.3M.

Since the first registration in 2013-Q2: 395 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 12 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
12 October 2026readyVilla · 4 BR 3,099 4,065,000 1,312
24 September 2026readyVilla · 4 BR 3,350 4,350,000 1,299
26 August 2026readyVilla · 4 BR 3,486 4,275,000 1,226
4 August 2026readyVilla · 3 BR 2,615 3,750,000 1,434
21 July 2026readyVilla · 4 BR 3,140 3,775,000 1,202
2 July 2026readyVilla · 4 BR 3,376 4,225,000 1,251
3 June 2026readyVilla · 3 BR 2,616 3,400,000 1,300
25 March 2026readyVilla · 3 BR 2,328 3,350,000 1,439
26 January 2026readyVilla · 3 BR 2,616 3,750,000 1,433
19 January 2026readyVilla · 4 BR 3,395 2,100,000 619

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationAl Yalayis 1 · Dubai Municipality community

Park · 160 mPark · 170 mPark · 220 mSpinneys · 390 mSpinneys · 1.5 kmSpinneys · 1.5 kmApproximate project location© OpenStreetMap contributors · Dubai Municipality · Makani
Approximate project location Malls and supermarkets Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

MallMall · 5.9 km
SupermarketSpinneys · 390 m
ParkPark · 160 m

Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors

New homes within 1.5 km

Open projects within 1.5 km of the pin: 2, with 776 units and villas.

No end date: 776

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Yalayis 1: 30

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Damac Islands 2 - Bahamas 2 0.3% Jun 2030 1,796 509
Damac Islands 2 - Bahamas 1 0.3% Jun 2030 1,822 465
Damac Islands 2 - Cuba 0.2% Jun 2030 1,648 447
Damac Islands 2 - Bermuda 0.2% Jun 2030 1,680 425
Damac Islands 2 - Tahiti 2 0.3% Jun 2030 1,932 392
Damac Islands 2 - Maui 0.2% Jun 2030 2,029 357
Damac Islands 2 - Barbados 1 0.2% Jun 2030 1,822 327
Damac Islands 2 - Barbados 2 0.2% Jun 2030 1,873 279
Damac Islands 2 - Tahiti 1 0.3% Jun 2030 1,619 263
Damac Islands 2 - Antigua 1 0.3% Dec 2030 1,932 210
Damac Islands - Maldives 2 14.1% Dec 2028 — 3
Damac Islands - Bora Bora 3 4.2% Dec 2028 — 2

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Yalayis 1

Developer in DLD data Al Aryam Phase One L.L.C · DLD developer no. 945

Projects registered
5
5 completed · 0 under construction · 0 not started
Units delivered
1,898
0 in the pipeline
Median build time
32 months
completed projects measured: 5

Completed a month or more after their DLD end date: 0 of 5 completed projects with both dates. In 4 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Questions about REEM-MIRA Community PH5

When was REEM-MIRA Community PH5 completed?

REEM-MIRA Community PH5 is recorded as completed on 30 September 2016 (DLD register of 1 November 2026).

Who is the developer of REEM-MIRA Community PH5?

Al Aryam Phase One L.L.C, as registered with DLD.

What is the DLD project number of REEM-MIRA Community PH5?

1342.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error