Al Mazaya Holding Company شركه المزايا القابضه 9 projects in the DLD register: 8 completed, 1 under construction, 0 not started or pending. 1 of the 1 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 9- Median time from start to completion: 35 months (8 completed projects).
- 1,494 units and villas in completed projects; 1 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 8 completed projects with both dates. In 7 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 1 of 1 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Al Mazaya Holding Company Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| The Villa685 · Wadi Al Safa 5 · The Villa | Under construction | 55% | Sep 2013 157 mo past | 157 mo | 1 | 88 |
| Qpoint LIWAN-PLOT R0091190 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Nov 2016 Completed | — | 117 | 15 |
| Qpoint LIWAN-PLOTR001895 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Jan 2014 Completed | — | 63 | 13 |
| Qpoint LIWAN-PLOT R0171182 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Jan 2017 Completed | — | 126 | 12 |
| Qpoint LIWAN-PLOT R0161191 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Feb 2012 Completed | — | 72 | 12 |
| Qpoint LIWAN-PLOT R0961214 · Wadi Al Safa 2 · Liwan1 | Completed | 100% | Aug 2015 Completed | — | 55 | 11 |
| Business Avenue BB21293 · Al Thanyah Fifth · DMCC Master Community | Completed | 100% | Nov 2010 Completed | — | 348 | 0 |
| Business Avenue BB11294 · Al Thanyah Fifth · DMCC Master Community | Completed | 100% | Jan 2011 Completed | — | 348 | 0 |
| Business Avenue AA1679 · Al Thanyah Fifth · DMCC Master Community | Completed | 100% | Mar 2011 Completed | — | 365 | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 1, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.