DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Al Qudra Estates L.L.C القدرة العقارية ذ.م.م DLD developer no. 1270 · Registered with DLD on 3 March 2019 · Licence 825002 3 projects in the DLD register: 2 completed, 1 under construction, 0 not started or pending. 1 of the 1 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
3
in the DLD register
Completed
2
590 units delivered
Not yet completed
1
235 units in the pipeline
Past DLD end date
1 / 1
under construction with an end date

Delivery record

Projects: 3
Completed 2Under construction 1
  • 590 units and villas in completed projects; 235 in projects not yet completed.
  • Completed a month or more after their DLD end date: 1 of 2 completed projects with both dates. In 0 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
  • Under construction past their DLD end date: 1 of 1 projects with an end date.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Al Qudra Estates L.L.C Most registered sales in the last 24 months first

Projects by Al Qudra Estates L.L.C
ProjectDLD status Built DLD end date / completion Past DLD end date Units Sales, 24 mo
Cherrywoods2171 · Al Yelayiss 1 Completed 100% Jun 2021 Completed— 378 66
Nad Al Sheba Gardens Phase 32484 · Nad Al Shiba First · Nad Al Sheba Gardens Under construction 97% Apr 2026 6 mo past6 mo 235 39
Nad Al Sheba Gardens Phase 22390 · Nad Al Shiba First · Nad Al Sheba Gardens Completed 100% Dec 2025 Completed— 212 8

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 1, all pinned

Nad Al Sheba Gardens Phase 3 · 75–100% builtNad Al Sheba Gardens Phase 3 · 75–100% builtMakani
75–100% built Approximate location (ringed)

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.