Aurora SPV 3 L.L.C أرورا اس بي في 3 ش.ذ.م.م 6 projects in the DLD register: 0 completed, 5 under construction, 1 not started or pending. 0 of the 5 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 6- 0 units and villas in completed projects; 2,735 in projects not yet completed.
- Under construction past their DLD end date: 0 of 5 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Aurora SPV 3 L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Athlon By Al Dar 13143 · Wadi Al Safa 5 | Under construction | 27.3% | May 2028 18 mo to go | 893 | 387 |
| Rise by Athlon 14044 · Wadi Al Safa 5 | Under construction | 3.7% | Dec 2029 37 mo to go | 650 | 356 |
| Athlon By Al Dar 23145 · Wadi Al Safa 5 | Under construction | 20.4% | Sep 2028 22 mo to go | 599 | 314 |
| Rise by Athlon 24045 · Wadi Al Safa 5 | Under construction | 3.7% | Jan 2030 38 mo to go | 407 | 308 |
| Rise by Athlon 34046 · Wadi Al Safa 5 | Not started | 0.5% | Jan 2030 38 mo to go | 120 | 113 |
| Rise by Athlon 44047 · Wadi Al Safa 5 | Under construction | 0.6% | Dec 2029 37 mo to go | 66 | 57 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 6, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.