Aurora SPV 1 L.L.C أرورا اس بي في 1 ش.ذ.م.م 5 projects in the DLD register: 0 completed, 5 under construction, 0 not started or pending. 0 of the 4 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 5- 0 units and villas in completed projects; 2,275 in projects not yet completed.
- Under construction past their DLD end date: 0 of 4 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Aurora SPV 1 L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Verdes by Haven 13188 · Wadi Al Safa 5 | Under construction | 17.7% | May 2028 18 mo to go | 988 | 658 |
| Haven By Aldar 22874 · Wadi Al Safa 5 | Under construction | 53.4% | — | 474 | 266 |
| Haven By Aldar 12873 · Wadi Al Safa 5 | Under construction | 61% | Nov 2027 12 mo to go | 462 | 188 |
| Haven By Aldar 32875 · Wadi Al Safa 5 | Under construction | 68.9% | Mar 2028 16 mo to go | 292 | 100 |
| Verdes by Haven 23189 · Wadi Al Safa 5 | Under construction | 27.5% | Jun 2028 19 mo to go | 59 | 56 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 5, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.