Citywalk Residential 1 L.L.C سيتي ووك ريزيدينشال 1 ش.ذ.م.م 26 projects in the DLD register: 17 completed, 6 under construction, 3 not started or pending. 0 of the 4 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 26- Median time from start to completion: 38 months (17 completed projects).
- 2,831 units and villas in completed projects; 1,924 in projects not yet completed.
- Completed a month or more after their DLD end date: 3 of 15 completed projects with both dates. In 10 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 0 of 4 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Citywalk Residential 1 L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| City Walk Crestlane 23530 · Al Wasl · City Walk | Under construction | 6.8% | Dec 2028 25 mo to go | 203 | 202 |
| City Walk Crestlane 13801 · Al Wasl · City Walk | Not started | 0.2% | Sep 2029 34 mo to go | 202 | 199 |
| City Walk Crestlane 33531 · Al Wasl · City Walk | Under construction | 4.6% | Dec 2028 25 mo to go | 195 | 195 |
| City Walk Crestlane 44286 · Al Wasl · City Walk | Not started | 0% | Apr 2030 41 mo to go | 204 | 186 |
| City Walk Crestlane 54274 · Al Wasl · City Walk | Not started | 0% | Apr 2030 41 mo to go | 161 | 151 |
| No.17, No.18a,No.18b and No.19 Citywalk Residential1781 · Al Wasl · City Walk | Completed | 100% | Jan 2017 Completed | 196 | 100 |
| Castleton2432 · Al Wasl · City Walk | Completed | 100% | Aug 2026 Completed | 214 | 74 |
| Laurel2451 · Al Wasl · City Walk | Completed | 100% | Jul 2026 Completed | 218 | 61 |
| Fern2481 · Al Wasl · City Walk | Completed | 100% | Oct 2026 Completed | 214 | 58 |
| Central Park at City Walk -Building 12147 · Al Wasl · City Walk | Completed | 94.4% | Oct 2021 Completed | 184 | 53 |
| Myrtle2381 · Al Wasl · City Walk | Completed | 100% | Apr 2025 Completed | 130 | 49 |
| Erin2556 · Al Wasl · City Walk | Completed | 100% | Jun 2026 Completed | 200 | 48 |
| NO.9 & NO.10 Citywalk Residential1717 · Al Wasl · City Walk | Completed | 100% | Dec 2016 Completed | 166 | 36 |
| Celadon2325 · Al Wasl · City Walk | Completed | 100% | Sep 2025 Completed | 161 | 36 |
| Verve City Walk3152 · Al Wasl · City Walk | Under construction | 13.7% | Sep 2028 22 mo to go | 440 | 35 |
| No. 4A, NO.4B, NO.5 Citywalk Residential1718 · Al Wasl · City Walk | Completed | 100% | Dec 2016 Completed | 148 | 29 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 9, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.