Continental Investments Lmd L.L.C كونتيننتال للاستثمار ال ام دي ش.ذ.م.م 10 projects in the DLD register: 6 completed, 4 under construction, 0 not started or pending. 0 of the 3 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 10- Median time from start to completion: 49 months (6 completed projects).
- 2,341 units and villas in completed projects; 1,108 in projects not yet completed.
- Completed a month or more after their DLD end date: 2 of 6 completed projects with both dates. In 3 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 0 of 3 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Continental Investments Lmd L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Rukan 32217 · Wadi Al Safa 7 · Rukan | Completed | 100% | Jul 2026 Completed | 1,089 | 510 |
| Taiyo Residences3757 · Jabal Ali First · Wasl Gate | Under construction | 12.1% | Dec 2027 13 mo to go | 379 | 356 |
| Rukan1570 · Wadi Al Safa 7 · Rukan | Completed | 100% | Jan 2023 Completed | 621 | 304 |
| The Pier3110 · Madinat Dubai Almelaheyah · Dubai Maritime City | Under construction | 48.4% | Dec 2026 1 mo to go | 282 | 184 |
| Boutique 232868 · Al Jadaf · Jaddaf Waterfront | Under construction | 64.9% | — | 328 | 118 |
| La Boutique3120 · Al Jadaf · Jaddaf Waterfront | Under construction | 52.5% | Dec 2026 1 mo to go | 119 | 113 |
| Rukan Residence2514 · Wadi Al Safa 7 · Rukan | Completed | 100% | Feb 2024 Completed | 153 | 64 |
| Continental Tower1380 · Marsa Dubai · Dubai Marina | Completed | 100% | Oct 2015 Completed | 224 | 49 |
| Marina Living2540 · Marsa Dubai · Dubai Marina | Completed | 100% | Jan 2026 Completed | 205 | 41 |
| Rukan22071 · Wadi Al Safa 7 · Rukan | Completed | 100% | Aug 2022 Completed | 49 | 11 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 4, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.