Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 2071Completed49 units

Rukan2 روكان2 Wadi Al Safa 7 · Rukan by Continental Investments Lmd L.L.CAll phases of Rukan Completed 30 August 2022 (DLD) DLD end date Aug 2022 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Aug 2022
DLD end date Aug 2022
Build time
50 months
Jul 2018 → Aug 2022
Latest sales
1,030 AED/sqft
5 sales
Developer
10 projects
6 completed · 2,341 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3). Latest DLD inspection: 100% built on 19 February 2025 (inspections: 7).
Every DLD inspection and every change in the register %, newest first
Date % built Source
19 February 2025 100% DLD inspection
12 May 2024 98% DLD register, archived export
9 February 2023 97.7% DLD inspection
5 August 2022 81% DLD register, archived export
1 August 2022 91% DLD inspection
26 December 2021 81.3% DLD inspection
24 May 2021 60% DLD inspection
25 October 2020 40.2% DLD inspection
14 February 2019 0.1% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
50 monthsActual build
50 months
Start date
1 July 2018
DLD end date
30 August 2022
Completion date
30 August 2022
Completion vs DLD end date
On the date

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
DLD project number
2071
Escrow agent
البنك العربي الافريقي الدولي (as registered)
Zoning authority
Dubai Development Authority (DDA)
Master project
Rukan
DLD area
Wadi Al Safa 7
Units · villas
0 · 49
Start → DLD end
Jul 2018 → Aug 2022
Registered units3 bed 49; sizes 2,127–2,158 sqft

Homes: villas 49.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: PROJECT CONSISTS OF (G+1) X 49 RESIDENTIAL VILLAS LOCATED IN WADI AL SAFA 7. THE VILLAS ARE DESIGNED TO HAVE A CONCRETE STRUCTURE WITH INTERNAL AND EXTERNAL FINISHES.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

Fewer than 5 sales with a size were registered in the first 90 days, so no launch price is shown.

Prices are over villas and townhouses, the type most sales in this project are.

Registered sales of villas and townhouses by bedroom count over the last 24 months, and the median AED/sqft of the latest ready sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
3 BR 11 1,030 (5) Nov 2025 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2020-Q3 → 2026-Q4

Median AED/sqft of registered sales per quarter (villas and townhouses). Source: DLD. Grey dashed line: DLD area Wadi Al Safa 7, median AED/sqft of ready sales of villas and townhouses by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 9; registered amount AED 14.5M.

Since the first registration in 2023-Q2: 58 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 5 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
5 October 2026readyVilla · 3 BR 2,813 2,750,000 978
20 August 2026readyVilla · 3 BR 2,816 2,900,000 1,030
1 April 2026readyVilla · 3 BR 2,816 2,900,000 1,030
12 March 2026readyVilla · 3 BR 1,895 2,825,000 1,491
7 January 2026readyVilla · 3 BR 4,222 3,150,000 746
4 March 2025readyVilla · 3 BR 1,894 2,675,000 1,412
10 February 2025readyVilla · 3 BR 1,894 2,600,000 1,373
9 January 2025readyVilla · 3 BR 1,894 2,500,000 1,320
10 December 2024readyVilla · 3 BR 1,894 2,540,000 1,341
9 December 2024readyVilla · 3 BR 4,830 3,400,000 704

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationWadi Al Safa 7 · Dubai Municipality community

Spinneys · 1.2 kmGems Metropole School · 1.2 kmWest Zone Supermarket · 1.3 kmPark · 1.4 kmPark · 1.4 kmPark · 1.5 kmApproximate project location© OpenStreetMap contributors · Dubai Municipality · Makani
Approximate project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

MallArabian Ranches Community Center · 2.5 km
SupermarketSpinneys · 1.2 km
HospitalKings Hospital · 8.6 km
SchoolGems Metropole School · 1.2 km
ParkPark · 1.4 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors

New homes within 1.5 km

Open projects within 1.5 km of the pin: 7, with 4,519 units and villas.

2022: 112027: 02028: 4732030: 4,035No end date: 0

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Wadi Al Safa 7: 6

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Reportage Village 1 25% Dec 2027 1,240 1,101
The Acres 2 & Estates 2 14.9% May 2028 — 208
The Acres 3 & Estates 14.9% Nov 2027 — 152
The Acres 25.2% — — 107
Mayfair Nexus by Seven Mayfair 0.6% Dec 2028 1,473 23
Palmarosa 97.8% Oct 2022 — 11

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Wadi Al Safa 7

Developer in DLD data Continental Investments Lmd L.L.C · DLD developer no. 958

Projects registered
10
6 completed · 4 under construction · 0 not started
Units delivered
2,341
1,108 in the pipeline
Median build time
49 months
completed projects measured: 6
Past the DLD end date
0
of 3 under construction with a DLD end date

Completed a month or more after their DLD end date: 2 of 6 completed projects with both dates. In 3 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Rukan

DLD lists 3 projects in the master project Rukan.

Rukan 3Completed · 100% · Jul 2026
RukanCompleted · 100% · Jan 2023
Rukan ResidenceCompleted · 100% · Feb 2024

Questions about Rukan2

When was Rukan2 completed?

Rukan2 is recorded as completed on 30 August 2022 (DLD register of 1 November 2026).

Who is the developer of Rukan2?

Continental Investments Lmd L.L.C, as registered with DLD.

What is the DLD project number of Rukan2?

2071.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error