DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 3126Under construction

The Acres 3 & Estates ذا إيكرز3 آند إستيتس Wadi Al Safa 7 by Dhre 2 Bts L.L.C 14.9% built (DLD register as of 1 November 2026) DLD end date Nov 2027 12 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

% built
14.9%
DLD register, 1 November 2026
Period elapsed
65%
Nov 2024 → Nov 2027
Latest sales
—
Fewer than 5 recent sales
Developer
13 projects
0 completed · 0 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built and period elapsed

1 November 2026
Built
14.9%Elapsed
65%

Two separate measures: one is DLD's % built, the other is time on the calendar.

Latest DLD register reading: 14.9% built on 1 November 2026 (register readings: 2). Latest DLD inspection: 14.9% built on 30 September 2026 (inspections: 8).
Every DLD inspection and every change in the register %, newest first
Date % built Source
30 September 2026 14.9% DLD inspection
24 June 2026 5.1% DLD inspection
16 March 2026 0.7% DLD inspection
31 December 2025 0.7% DLD inspection
2 October 2025 0.7% DLD inspection
7 July 2025 0.7% DLD inspection
7 April 2025 0.3% DLD inspection
3 June 2024 0% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗ Period elapsed: our calculation from DLD’s start and end dates.

Our completion calculation

Recent pace
2.3 pt/month
5.1% on 24 June 2026 → 14.9% on 1 November 2026
At the register date
14.9%
1 November 2026

Our calculation from DLD readings. It describes the recent pace only; it is not a forecast of the completion date.

Site timeline

± 6 months
Works startedMar 2026 ± 6 months
Structure risingMar 2026 ± 6 months
Topped outNot seen yet
FinishedNot seen yet

Each date is ± 6 months. This is our reading, not DLD's; no image is shown. Read from imagery dated 23 October 2022 to 25 May 2026; method imagery-v1.

Changes in the DLD register

1 Nov 2026Construction completed: 14.9% → 14.9%.

Source: DLD projects register exports, compared by CraneScore. Dates and progress are those in the Dubai Land Department projects register on each register date, not inspection dates. DLD can revise the end date; we keep every register reading from 28 October 2026 on and list the changes here.

Inspection photos and reports

DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.

CraneScore links to DLD and does not copy or host its photos or reports.

DLD registration

DLD services ↗
DLD project number
3126
Escrow agent
Abu Dhabi Commercial Bank
Zoning authority
Dubai Development Authority (DDA)
DLD area
Wadi Al Safa 7
Units · villas
0 · 0
Start → DLD end
Nov 2024 → Nov 2027
Registered units3 bed 25 · 4 bed 83 · 5+ bed 183; sizes 4,087–6,913 sqft

Homes: villas 291.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Consists of 291 Villas (G+1, G+2); 3, 4, 5, 6 & 7- Bedrooms Villas; including 16 frozen plots as listed below. LOCI and U+A are the project?s architects : LOCI: G+1 = 36 Villas, and G+2 = 7 villas , including 5 frozen plots. U+A: G+1 = 104 Villas, and G+2 = 144 Villas, including 11 frozen plots.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

No off-plan sales are registered for this project since 2020, so there is no launch price.

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Rents in DLD area Wadi Al Safa 7

New Ejari rent contracts for apartments across DLD area Wadi Al Safa 7, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.

Bedrooms Median annual rent New contracts Change on a year earlier
Studio AED 44,000 130 +10%
1 BR AED 55,000 120 0%
2 BR AED 87,999 80 +7.3%
3 BR AED 120,000 13 +18.3%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Looking for a unit in this or similar projects?

Tell us what you are looking for in The Acres 3 & Estates or similar projects. We reply by e-mail, and your request stays with CraneScore.

We send a 6-digit code to confirm it.
Bedrooms

Estimated value range

Not enough registered off-plan sales for an estimate (at least 5 of one bedroom count in 12 months).

Automated estimate, not a valuation

Track this unit

Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.

Resale asking prices against the original price

Fewer than 5 resale offers with an original price are tracked for this project.

Across all Dubai off-plan resale offers we track: -3.9% (1,105 offers).

Median asking premium by share of the price already paid (number of offers); shown from 5 offers
Paid to the developer This project All Dubai
0–30% paid—0% (9)
30–50% paid—-5% (51)
50–70% paid—-1.5% (65)
70% paid or more—-3.5% (45)

Asking prices of off-plan resale offers we track, compared with each offer's original price, with the 4% DLD fee removed on both sides. A negative value means asking below the original price. Only aggregates of at least 5 offers are shown; no individual offer, seller or agent is.

Thinking of selling your unit?

Thinking of reselling your unit in The Acres 3 & Estates? Leave your details and we reply by e-mail. Your request stays with CraneScore.

We send a 6-digit code to confirm it.

Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Nov 2027); move it with the slider.

A scenario from your own inputs, not this project's verified payment plan.

Common plans

Plan shares add up to 100% (must be 100%).

Handover
Nov 2027
Paid by handover
AED 1,045,000
Fees included
Price paid at handover
100%
Total cost
AED 1,045,000
Fees: AED 45,000

Payments per quarter

AED

Payments per quarter, AED, fees included. Illustration from your inputs.

The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.

Mortgage for a unit here

Questions about financing a unit in The Acres 3 & Estates? Leave your details and we reply by e-mail. Your request stays with CraneScore.

We send a 6-digit code to confirm it.

LocationWadi Al Safa 7 · Dubai Municipality community

Approximate project location© OpenStreetMap contributors · Dubai Municipality · Makani
Approximate project location

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

MallCityland Mall · 2.4 km
SupermarketWest Zone Supermarket · 2.3 km
HospitalKings Hospital · 8.8 km
SchoolGems Metropole School · 2.4 km
ParkPark · 1.6 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors

New homes within 1.5 km

Open projects within 1.5 km of the pin: 11, with 2,432 units and villas.

2027: 02028: 02029: 02030: 2,432No end date: 0

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Wadi Al Safa 7: 5

Open projects in the same DLD area with a DLD end year from 2026 to 2028, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Reportage Village 1 25% Dec 2027 1,240 1,101
The Acres 2 & Estates 2 14.9% May 2028 — 208
Mayfair Nexus by Seven Mayfair 0.6% Dec 2028 1,473 23

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Wadi Al Safa 7

Developer in DLD data Dhre 2 Bts L.L.C · DLD developer no. 1510

Projects registered
13
0 completed · 9 under construction · 4 not started
Units delivered
0
2,895 in the pipeline
Past the DLD end date
0
of 8 under construction with a DLD end date

Dhre 2 Bts L.L.C is one of 3 DLD-registered developers we list together as Dubai Holding Real Estate (DHRE). See the group

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Questions about The Acres 3 & Estates

When is The Acres 3 & Estates's handover?

DLD lists an end date of Nov 2027 (register of 1 November 2026); the SPA sets the handover terms.

Is The Acres 3 & Estates past its DLD end date?

No. Its DLD end date is Nov 2027, 12 months after the register of 1 November 2026.

How far along is The Acres 3 & Estates?

14.9% built in the DLD register of 1 November 2026.

Who is the developer of The Acres 3 & Estates?

Dhre 2 Bts L.L.C, as registered with DLD.

What is the DLD project number of The Acres 3 & Estates?

3126.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error