Dhre 2 Bts L.L.C دي اتش ار اي 2 بي تي اس ش.ذ.م.م 13 projects in the DLD register: 0 completed, 9 under construction, 4 not started or pending. 0 of the 8 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 13- 0 units and villas in completed projects; 2,895 in projects not yet completed.
- Under construction past their DLD end date: 0 of 8 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Dhre 2 Bts L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Jumeirah Residences Emirates Towers3820 · Trade Center Second | Under construction | 4.2% | Sep 2030 46 mo to go | 754 | 749 |
| THE EDIT at d34177 · Zaabeel Second · Business Park | Not started | 0.2% | Jan 2030 38 mo to go | 557 | 313 |
| Atelis at d33750 · Zaabeel Second · Business Park | Under construction | 1.4% | Aug 2029 33 mo to go | 280 | 281 |
| The Acres 2 & Estates 23586 · Wadi Al Safa 7 | Under construction | 14.9% | May 2028 18 mo to go | — | 208 |
| The Acres 3 & Estates3126 · Wadi Al Safa 7 | Under construction | 14.9% | Nov 2027 12 mo to go | — | 152 |
| The Acres3019 · Wadi Al Safa 7 | Under construction | 25.2% | — | — | 107 |
| Bluewaters Bay2530 · Marsa Dubai | Under construction | 37% | Mar 2027 4 mo to go | 679 | 91 |
| Design Quarter2607 · Zaabeel Second · Business Park | Under construction | 40.8% | Feb 2027 3 mo to go | 564 | 45 |
| Jumeirah Asora Bay3445 · Jumeirah First · La Mer | Under construction | 4.4% | Mar 2029 28 mo to go | 30 | 30 |
| Bulgari Lighthouse Dubai2507 · Island 2 · Jumeira Bay | Under construction | 80% | Mar 2027 4 mo to go | 31 | 5 |
| Jumeirah Residences - Asora Bay - Ocean Mansions3526 · Jumeirah First · La Mer | Not started | 0.5% | Mar 2029 28 mo to go | — | 0 |
| Project 4614, Jumeirah First4614 · Jumeirah First · La Mer | Pending | 0% | Apr 2030 41 mo to go | — | 0 |
| Project 2906, Nad Al Shiba First2906 · Nad Al Shiba First · Nad Al Sheba Gardens | Pending | 0% | — | — | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 13, 12 pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.