DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Digo Real Estate Development (Br Of Invest Group Overseas (L L C) ) دي اي جي او التطوير العقاري (فرع من مجموعة الاستثمار لما وراء البحار (ش ذ م م )) DLD developer no. 1328 · Registered with DLD on 5 April 2021 · Licence ..767971 8 projects in the DLD register: 3 completed, 4 under construction, 1 not started or pending. 1 of the 3 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
8
in the DLD register
Completed
3
597 units delivered
Not yet completed
5
849 units in the pipeline
Past DLD end date
1 / 3
under construction with an end date

Delivery record

Projects: 8
Completed 3Under construction 4Not started or pending 1
  • Median time from start to completion: 24 months (3 completed projects).
  • 597 units and villas in completed projects; 849 in projects not yet completed.
  • Completed a month or more after their DLD end date: 0 of 2 completed projects with both dates. In 2 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
  • Under construction past their DLD end date: 1 of 3 projects with an end date.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Digo Real Estate Development (Br Of Invest Group Overseas (L L C) ) Most registered sales in the last 24 months first

Projects by Digo Real Estate Development (Br Of Invest Group Overseas (L L C) )
ProjectDLD status Built DLD end date / completion Past DLD end date Units Sales, 24 mo
PELaGOS By IGO3246 · Marsa Dubai · Dubai Marina Under construction 84.2% Mar 2026 7 mo past7 mo 296 269
Society House Downtown Dubai2647 · Burj Khalifa · DownTown Dubai Completed 100% Sep 2026 Completed— 417 59
Ayaan Heights I3610 · Bukadra Under construction 20.3% Mar 2028 16 mo to go— 130 43
Azura Residences3080 · Palm Deira Under construction 69.1% — — 148 38
Catch Residences By IGO2339 · Al Barsha South Fourth · Jumeirah Village Circle Completed 100% Jan 2024 Completed— 140 28
The Estate - II2257 · Jabal Ali First · Al Furjan Completed 100% Jun 2022 Completed— 40 2
The Mansions by MAG3779 · Jabal Ali First · Al Furjan Under construction 9.3% Apr 2027 5 mo to go— 15 0
The Winslow3634 · Bukadra Not started 0% Jun 2028 19 mo to go— 260 0

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 5, all pinned

Azura Residences · 50–75% builtPELaGOS By IGO · 75–100% built2 projects2The Mansions by MAG · Under construction, 0–25% builtAzura Residences · 50–75% builtPELaGOS By IGO · 75–100% built2 projects2The Mansions by MAG · Under construction, 0–25% builtMakani
Under construction, 0–25% built 50–75% built 75–100% built Not started

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.