Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 3634Not started260 units

The Winslow ذا وينسلو Bukadra by Digo Real Estate Development (Br Of Invest Group Overseas (L L C) ) DLD status: Not started (DLD register as of 1 November 2026) DLD end date Jun 2028 19 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

% built
0%
DLD register, 1 November 2026
Registered start
Dec 2025
DLD end date Jun 2028
Latest sales
—
Fewer than 5 recent sales
Developer
8 projects
3 completed · 597 units delivered

Completion

DLD status: Not started. 0% built, DLD end date 30 June 2028. DLD Project Status shows inspection reports once works begin.

DLD register readings
Date % built DLD end dateDLD status
1 November 2026 0% 30 June 2028Not started
28 October 2026 0% 30 June 2028Not started

Source: DLD projects register, export of 1 November 2026.

Inspection photos and reports

DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.

CraneScore links to DLD and does not copy or host its photos or reports.

Building permits

1 of 1 buildings

Buildings on the project’s plots: 1, on construction permits: 1, as Dubai Municipality lists them.

Furthest stage reached: Site works.

Work not started
Site works
Foundations
Structure
Masonry
Finishes
Final works
Completed
Buildings
1
1 on construction permits
Permit status
Open
461127
Issued
17 November 2025
Work start
12 March 2026
Consultant · contractor
NEXT ENGINEERING CONSULTANTS L.L.C · TAK CONSTRUCTION (L.L.C)
Buildings by the furthest work stage Dubai Municipality lists
Work stage Buildings
Site works1

Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.

DLD registration

DLD services ↗
DLD project number
3634
Escrow agent
First Abu Dhabi Bank P.J.S.C.
Zoning authority
Dubai Municipality
DLD area
Bukadra
Units · villas
260 · 0
Start → DLD end
Dec 2025 → Jun 2028
Registered units1 bed 130 · 2 bed 49 · 3 bed 11; sizes 763–1,205 sqft

Also registered: offices 62 · shops and showrooms 8.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: B +G+4P+HC+18+Roof

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

LocationBu Kadra · Dubai Municipality community

Delight Grocery · 630 mShabab Al Madina · 720 mKhalid Abdurdah Grocery · 740 mEden Park · 1.4 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationCreek Metro Station · Green Metro line · 4.6 km
MallSobha Mall (Under Construction) · 2.4 km
SupermarketDelight Grocery · 630 m
HospitalHospital · 2.7 km
SchoolNorth London Collegiate School · 1.9 km
ParkEden Park · 1.4 km
BeachBeach · 1.8 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 50, with 21,177 units and villas.

2025: 4552027: 2,9862028: 3,4812029: 3,1762030: 3,275No end date: 7,804

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Bu Kadra: 31

Open projects in the same DLD area with a DLD end year from 2027 to 2029, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Skyscape 38.3% Dec 2029 2,426 1,473
Claydon House By Ellington 15.7% Dec 2027 2,008 400
Parkway By Prestige One 10.9% Jan 2028 1,955 263
The Highgrove 7% Dec 2028 2,453 229
Imtiaz Symphony Tower 6.3% Jun 2029 2,450 221
Belmore Residences 6.5% Dec 2027 2,211 181
Wynwood Horizon by Imtiaz 9.6% Oct 2028 2,319 131
The Caden By Prescott 0.5% May 2028 2,279 107
Riverton House 0% Dec 2027 — 75
Future Residence 0% Jun 2027 1,956 72
The Waterway by Prestige One 14.7% Jun 2027 1,864 60
R Home MH 1.8% Aug 2029 2,630 52

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Bu Kadra

Developer in DLD data Digo Real Estate Development (Br Of Invest Group Overseas (L L C) ) · DLD developer no. 1328

Projects registered
8
3 completed · 4 under construction · 1 not started
Units delivered
597
849 in the pipeline
Median build time
24 months
completed projects measured: 3
Past the DLD end date
1
of 3 under construction with a DLD end date

Completed a month or more after their DLD end date: 0 of 2 completed projects with both dates. In 2 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error