DLD project no. 3160Under construction1,852 units
Skyscape سكاي سكيب 38.3% built (DLD register as of 1 November 2026) · DLD end date Dec 2029 · 37 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

CompletionDLD readings of % built, beside the share of the planned period gone
% built and period elapsed
1 November 2026Two separate measures: one is DLD's % built, the other is time on the calendar.
| Date | % built | Source |
|---|---|---|
| 21 September 2026 | 38.3% | DLD inspection |
| 16 June 2026 | 30.1% | DLD inspection |
| 31 March 2026 | 23.2% | DLD inspection |
| 4 July 2025 | 11.9% | DLD inspection |
| 22 July 2024 | 0% | DLD inspection |
Source: Dubai Land Department projects register, as of 1 November 2026. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗ Period elapsed: our calculation from DLD’s start and end dates.
Our completion calculation
Our calculation from DLD readings. It describes the recent pace only; it is not a forecast of the completion date.
Site timeline
± 6 monthsEach date is ± 6 months. This is our reading, not DLD's; no image is shown. Read from imagery dated 9 August 2022 to 25 May 2026; method imagery-v1.
Changes in the DLD register
Source: DLD projects register exports, compared by CraneScore. Dates and progress are those in the Dubai Land Department projects register on each register date, not inspection dates. DLD can revise the end date; we keep every register reading from 28 October 2026 on and list the changes here.
Inspection photos and reports
DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.
CraneScore links to DLD and does not copy or host its photos or reports.
Building permits
3 of 4 buildingsBuildings on the project’s plots: 4, on construction permits: 1, as Dubai Municipality lists them.
Furthest stage reached: Finishes.
| Work stage | Buildings |
|---|---|
| Structure | 1 |
| Finishes | 3 |
Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.
DLD registration
DLD services ↗Also registered: shops and showrooms 7.
Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: Residential and commercial development consists of 3 buildings Building 1 (Tower A): Basement + Ground + 5 Podium+ 73 Floor + Roof +Upper Roof Building 2 (Tower B): Basement + Ground + 4 Podium+ 50 Floor + Roof +Upper Roof Building 3 (Tower C): Basement + Ground + 3 Podium+ 36 Floor + Roof +Upper Roof
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
Dubai Statistics Center residential price index (flats), 2024-Q4 to 2026-Q2: +5.5%.
Prices are over apartments, the type most sales in this project are.
| Bedrooms | Launch price | Latest registered sales | Change |
|---|---|---|---|
| 1 BR | 2,410 (231) | 2,400 (30) | -0.4% |
| 2 BR | 2,411 (126) | 2,575 (10) | +6.8% |
| 3 BR | 2,515 (24) | 2,610 (9) | +3.8% |
| Bedrooms | Sales, 24 months | Latest median AED/sqft | Latest sales |
|---|---|---|---|
| 1 BR | 835 | 2,400 (30) | May 2026 – Nov 2026 |
| 2 BR | 501 | 2,575 (10) | May 2026 – Nov 2026 |
| 3 BR | 113 | 2,610 (9) | May 2026 – Nov 2026 |
| 4 BR | 24 | 2,741 (5) | Nov 2025 – Nov 2026 |
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Median AED/sqft by quarter
2024-Q4 → 2026-Q4| Quarter | Registered sales | Median AED/sqft | DLD area Bukadra |
|---|---|---|---|
| 2024-Q4 | 340 (off-plan 340, ready 0) | 2,411 | 2,390 |
| 2025-Q1 | 284 (off-plan 284, ready 0) | 2,515 | 2,373 |
| 2025-Q2 | 280 (off-plan 280, ready 0) | 2,500 | 2,429 |
| 2025-Q3 | 197 (off-plan 197, ready 0) | 2,454 | 2,517 |
| 2025-Q4 | 204 (off-plan 204, ready 0) | 2,424 | 2,424 |
| 2026-Q1 | 94 (off-plan 94, ready 0) | 2,449 | 2,540 |
| 2026-Q2 | 40 (off-plan 40, ready 0) | 2,415 | 2,487 |
| 2026-Q3 | 26 (off-plan 26, ready 0) | 2,430 | 2,560 |
| 2026-Q4 | 10 (off-plan 10, ready 0) | 2,460 | 2,450 |
Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Bukadra, median AED/sqft of off-plan sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.
Registered sales per quarter
| Quarter | Registered sales | Median AED/sqft | DLD area Bukadra |
|---|---|---|---|
| 2024-Q4 | 340 (off-plan 340, ready 0) | 2,411 | 2,390 |
| 2025-Q1 | 284 (off-plan 284, ready 0) | 2,515 | 2,373 |
| 2025-Q2 | 280 (off-plan 280, ready 0) | 2,500 | 2,429 |
| 2025-Q3 | 197 (off-plan 197, ready 0) | 2,454 | 2,517 |
| 2025-Q4 | 204 (off-plan 204, ready 0) | 2,424 | 2,424 |
| 2026-Q1 | 94 (off-plan 94, ready 0) | 2,449 | 2,540 |
| 2026-Q2 | 40 (off-plan 40, ready 0) | 2,415 | 2,487 |
| 2026-Q3 | 26 (off-plan 26, ready 0) | 2,430 | 2,560 |
| 2026-Q4 | 10 (off-plan 10, ready 0) | 2,460 | 2,450 |
Registered sales per quarter, off-plan and ready units. Source: DLD.
Rents in DLD area Bukadra
New Ejari rent contracts for apartments across DLD area Bukadra, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.
| Bedrooms | Median annual rent | New contracts | Change on a year earlier |
|---|---|---|---|
| 2 BR | AED 110,000 | 13 | -4.3% |
New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.
Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.
Registered sales
The newest sales DLD has registered in this project, as DLD publishes them.
| Date | Market | Type | Size (sqft) | Price (AED) | AED/sqft |
|---|---|---|---|---|---|
| 3 November 2026 | off-plan | Apartment · 1 BR | 828 | 2,007,027 | 2,424 |
| 30 October 2026 | off-plan | Apartment · 2 BR | 1,537 | 4,062,458 | 2,643 |
| 23 October 2026 | off-plan | Apartment · 1 BR | 846 | 2,008,585 | 2,374 |
| 21 October 2026 | off-plan | Apartment · 3 BR | 1,712 | 4,571,921 | 2,671 |
| 19 October 2026 | off-plan | Apartment · 1 BR | 767 | 1,861,091 | 2,426 |
| 8 October 2026 | off-plan | Apartment · 2 BR | 1,725 | 4,355,676 | 2,525 |
| 8 October 2026 | off-plan | Apartment · 1 BR | 787 | 1,936,168 | 2,460 |
| 5 October 2026 | off-plan | Apartment · 3 BR | 1,712 | 4,392,101 | 2,565 |
| 5 October 2026 | off-plan | Apartment · 2 BR | 1,512 | 4,037,627 | 2,670 |
| 5 October 2026 | off-plan | Apartment · 1 BR | 846 | 2,000,001 | 2,364 |
Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
Looking for a unit in this or similar projects?
Tell us what you are looking for in Skyscape or similar projects. We reply by e-mail, and your request stays with CraneScore.
Estimated value range
| Bedrooms | Range, AED | Based on | Compared at |
|---|---|---|---|
| 1 BR | 1,940,000 – 2,100,000 | 205 sales, 12 months | This project |
| 2 BR | 3,640,000 – 3,940,000 | 57 sales, 12 months | This project |
| 3 BR | 4,020,000 – 4,420,000 | 35 sales, 12 months | This project |
| 4 BR | 7,750,000 – 7,870,000 | 5 sales, 12 months | This project |
Estimate as of 5 November 2026 Track this unit
Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.
Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Dec 2029); move it with the slider.
A scenario from your own inputs, not this project's verified payment plan.
Common plans
Plan shares add up to 100% (must be 100%).
Payments per quarter
AED| Quarter | Paid |
|---|---|
| 2026-Q4 | AED 245,000 · AED 245,000 paid so far |
| 2027-Q2 | AED 100,000 · AED 345,000 paid so far |
| 2028-Q1 | AED 100,000 · AED 445,000 paid so far |
| 2028-Q3 | AED 100,000 · AED 545,000 paid so far |
| 2029-Q2 | AED 100,000 · AED 645,000 paid so far |
| 2029-Q4 | AED 400,000 · AED 1,045,000 paid so far |
Payments per quarter, AED, fees included. Illustration from your inputs.
The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.
Mortgage for a unit here
Questions about financing a unit in Skyscape? Leave your details and we reply by e-mail. Your request stays with CraneScore.
LocationBu Kadra · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
School ratings: KHDA’s school directory ↗ · Report a wrong location
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 49, with 20,013 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2026 | 1 | 553 |
| 2027 | 18 | 6,373 |
| 2028 | 11 | 3,741 |
| 2029 | 8 | 1,324 |
| 2030 | 5 | 3,275 |
| No end date | 6 | 4,747 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Bu Kadra: 31
Open projects in the same DLD area with a DLD end year from 2028 to 2030, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Skyvue | 10.5% | Mar 2030 | 2,989 | 2,104 |
| Parkway By Prestige One | 10.9% | Jan 2028 | 1,955 | 263 |
| The Highgrove | 7% | Dec 2028 | 2,453 | 229 |
| Imtiaz Symphony Tower | 6.3% | Jun 2029 | 2,450 | 221 |
| Wynwood Horizon by Imtiaz | 9.6% | Oct 2028 | 2,319 | 131 |
| The Caden By Prescott | 0.5% | May 2028 | 2,279 | 107 |
| R Home MH | 1.8% | Aug 2029 | 2,630 | 52 |
| Ayaan Heights I | 20.3% | Mar 2028 | 2,219 | 43 |
| Mia Tower | 0% | Feb 2028 | — | 0 |
| The Winslow | 0% | Jun 2028 | — | 0 |
| Eaton Square | 5.4% | Jun 2028 | — | 0 |
| Future Avenue Tower | 0% | Aug 2028 | — | 0 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Sobha L.L.C · DLD developer no. 966
Completed a month or more after their DLD end date: 2 of 17 completed projects with both dates. In 10 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
Sobha L.L.C is one of 6 DLD-registered developers we list together as Sobha. See the group
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Questions about Skyscape
When is Skyscape's handover?
DLD lists an end date of Dec 2029 (register of 1 November 2026); the SPA sets the handover terms.
Is Skyscape past its DLD end date?
No. Its DLD end date is Dec 2029, 37 months after the register of 1 November 2026.
How far along is Skyscape?
38.3% built in the DLD register of 1 November 2026.
Who is the developer of Skyscape?
Sobha L.L.C, as registered with DLD.
What is the DLD project number of Skyscape?
3160.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error