Sobha L.L.C شوبا ش.ذ.م.م 45 projects in the DLD register: 17 completed, 22 under construction, 6 not started or pending. 0 of the 13 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 45- Median time from start to completion: 41 months (17 completed projects).
- 7,444 units and villas in completed projects; 30,108 in projects not yet completed.
- Completed a month or more after their DLD end date: 2 of 17 completed projects with both dates. In 10 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 0 of 13 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Sobha L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Sobha Solis3334 · Al Hebiah First · Motor City | Under construction | 17.9% | Dec 2028 25 mo to go | 2,351 | 2,143 |
| Skyvue3435 · Bukadra | Under construction | 10.5% | Mar 2030 40 mo to go | 2,738 | 2,104 |
| Sobha Orbis3070 · Al Hebiah First · Motor City | Under construction | 18.2% | Dec 2028 25 mo to go | 3,002 | 1,895 |
| Skyscape3160 · Bukadra | Under construction | 38.3% | Dec 2029 37 mo to go | 1,852 | 1,473 |
| Sobha Central Phase I3713 · Jabal Ali First · DMCC-EZ2 | Under construction | 7.1% | Jun 2030 43 mo to go | 2,383 | 1,192 |
| Sobha Central Phase II4042 · Jabal Ali First · DMCC-EZ2 | Under construction | 6.4% | Jun 2030 43 mo to go | 2,143 | 809 |
| Sobha One2948 · Ras Al Khor Industrial First | Under construction | 86.2% | — | 3,057 | 774 |
| Sobha Central4328 · Jabal Ali First · DMCC-EZ2 | Under construction | 2.4% | Dec 2031 61 mo to go | 2,169 | 614 |
| Sobha Hartland - The Crest2447 · Al Merkadh · Sobha Hartland | Completed | 100% | Dec 2025 Completed | 1,518 | 424 |
| 310 Riverside Crescent3067 · Bukadra | Under construction | 50.2% | — | 913 | 382 |
| The Woods4485 · Al Yufrah 1 | Not started | 0% | Dec 2030 49 mo to go | 1,267 | 319 |
| Sobha Hartland - Crest Grande2482 · Al Merkadh · Sobha Hartland | Completed | 100% | Apr 2026 Completed | 985 | 294 |
| The Element at Sobha One3540 · Ras Al Khor Industrial First | Under construction | 11.1% | Dec 2029 37 mo to go | 401 | 279 |
| Elwood Estates3602 · Al Yufrah 1 | Under construction | 14.4% | Jun 2028 19 mo to go | — | 267 |
| 340 Riverside Crescent3082 · Bukadra | Under construction | 55% | — | 769 | 252 |
| 350 Riverside Crescent3083 · Bukadra | Under construction | 57.9% | — | 750 | 238 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 28, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.