DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai Investment Real Estate (L L C) دبي للاستثمار العقاري (ش ذ م م) DLD developer no. 278 · Registered with DLD on 7 January 2008 · Licence 573664 7 projects in the DLD register: 4 completed, 3 under construction, 0 not started or pending. 1 of the 3 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
7
in the DLD register
Completed
4
2,321 units delivered
Not yet completed
3
864 units in the pipeline
Past DLD end date
1 / 3
under construction with an end date

Delivery record

Projects: 7
Completed 4Under construction 3
  • Median time from start to completion: 39 months (4 completed projects).
  • 2,321 units and villas in completed projects; 864 in projects not yet completed.
  • Completed a month or more after their DLD end date: 0 of 4 completed projects with both dates. In 4 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
  • Under construction past their DLD end date: 1 of 3 projects with an end date.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Dubai Investment Real Estate (L L C) Most registered sales in the last 24 months first

Projects by Dubai Investment Real Estate (L L C)
ProjectDLD status Built DLD end date / completion Past DLD end date Units Sales, 24 mo
Ritaj1042 · Dubai Investment Park Second Completed 100% Jun 2011 Completed— 1,066 291
Violet Tower2824 · Al Barsha South Fourth · Jumeirah Village Circle Under construction 90.2% Jun 2026 4 mo past4 mo 287 285
Mirdif Hills - Asayel Avenue3389 · Mirdif Under construction 33.1% May 2027 6 mo to go— 193 109
Mirdif HILLS- Nasayem Avenue1834 · Mirdif Completed 100% Mar 2020 Completed— 407 79
Mirdif HILLS- Al Multaqa Avenue1835 · Mirdif Completed 100% Aug 2021 Completed— 489 43
Mirdif HILLS- Janayen Avenue1073 · Mirdif Completed 100% Jan 2020 Completed— 359 38
Al Vista3802 · Bukadra Under construction 9.5% Oct 2027 11 mo to go— 384 3

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 3, all pinned

Violet Tower · 75–100% builtMirdif Hills - Asayel Avenue · 25–50% builtAl Vista · Under construction, 0–25% builtViolet Tower · 75–100% builtMirdif Hills - Asayel Avenue · 25–50% builtAl Vista · Under construction, 0–25% builtMakani
Under construction, 0–25% built 25–50% built 75–100% built

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.