J A Parks L.L.C جي أيه باركس ش.ذ.م.م 1 projects in the DLD register: 0 completed, 1 under construction, 0 not started or pending. 1 of the 1 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 1- 0 units and villas in completed projects; 511 in projects not yet completed.
- Under construction past their DLD end date: 1 of 1 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by J A Parks L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Damac City2374 · Al Wasl · Dubai Water Canal | Under construction | 72.8% | Dec 2025 10 mo past | 10 mo | 511 | 118 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 1, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.