Majid Al Futtaim Tilal Al Ghaf Phase A L.L.C ماجد الفطيم تلال الغاف المرحلة أ ذ.م.م 9 projects in the DLD register: 3 completed, 6 under construction, 0 not started or pending. 3 of the 3 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 9- Median time from start to completion: 47 months (3 completed projects).
- 1,724 units and villas in completed projects; 148 in projects not yet completed.
- Completed a month or more after their DLD end date: 2 of 3 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 3 of 3 projects with an end date, by a median of 3 months.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Majid Al Futtaim Tilal Al Ghaf Phase A L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Aura2259 · Al Hebiah Fourth · Tilal Al Ghaf | Completed | 100% | Oct 2025 Completed | — | 808 | 257 |
| Elan2205 · Al Hebiah Fourth · Tilal Al Ghaf | Completed | 100% | Nov 2023 Completed | — | 916 | 151 |
| Amara2858 · Al Hebiah Fourth · Tilal Al Ghaf | Under construction | 70.8% | — | — | 116 | 33 |
| Plagette 322827 · Al Hebiah Fourth · Tilal Al Ghaf | Under construction | 60.6% | — | — | 32 | 5 |
| Harmony2221 · Al Hebiah Fourth · Tilal Al Ghaf | Completed | 100% | Dec 2025 Completed | — | — | 2 |
| Elysian Mansions2054 · Al Hebiah Fourth · Tilal Al Ghaf | Under construction | 95% | Mar 2025 19 mo past | 19 mo | — | 0 |
| Alaya2322 · Al Hebiah Fourth · Tilal Al Ghaf | Under construction | 91.5% | Jul 2026 3 mo past | 3 mo | — | 0 |
| Lanai Island2498 · Al Hebiah Fourth · Tilal Al Ghaf | Under construction | 60.6% | Sep 2026 1 mo past | 1 mo | — | 0 |
| Serenity Mansions2718 · Al Hebiah Fourth · Tilal Al Ghaf | Under construction | 32.4% | — | — | — | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 6, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.