DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Majid Al Futtaim Tilal Al Ghaf Phase A L.L.C ماجد الفطيم تلال الغاف المرحلة أ ذ.م.م DLD developer no. 1228 · Registered with DLD on 11 February 2018 · Licence 795156 9 projects in the DLD register: 3 completed, 6 under construction, 0 not started or pending. 3 of the 3 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026

Projects
9
in the DLD register
Completed
3
1,724 units delivered
Not yet completed
6
148 units in the pipeline
Past DLD end date
3 / 3
under construction with an end date

Delivery record

Projects: 9
Completed 3Under construction 6
  • Median time from start to completion: 47 months (3 completed projects).
  • 1,724 units and villas in completed projects; 148 in projects not yet completed.
  • Completed a month or more after their DLD end date: 2 of 3 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
  • Under construction past their DLD end date: 3 of 3 projects with an end date, by a median of 3 months.

One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.

Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.

Completed projects: launch to resale

Loading…

Projects by Majid Al Futtaim Tilal Al Ghaf Phase A L.L.C Most registered sales in the last 24 months first

Projects by Majid Al Futtaim Tilal Al Ghaf Phase A L.L.C
ProjectDLD status Built DLD end date / completion Past DLD end date Units Sales, 24 mo
Aura2259 · Al Hebiah Fourth · Tilal Al Ghaf Completed 100% Oct 2025 Completed— 808 257
Elan2205 · Al Hebiah Fourth · Tilal Al Ghaf Completed 100% Nov 2023 Completed— 916 151
Amara2858 · Al Hebiah Fourth · Tilal Al Ghaf Under construction 70.8% — — 116 33
Plagette 322827 · Al Hebiah Fourth · Tilal Al Ghaf Under construction 60.6% — — 32 5
Harmony2221 · Al Hebiah Fourth · Tilal Al Ghaf Completed 100% Dec 2025 Completed— — 2
Elysian Mansions2054 · Al Hebiah Fourth · Tilal Al Ghaf Under construction 95% Mar 2025 19 mo past19 mo — 0
Alaya2322 · Al Hebiah Fourth · Tilal Al Ghaf Under construction 91.5% Jul 2026 3 mo past3 mo — 0
Lanai Island2498 · Al Hebiah Fourth · Tilal Al Ghaf Under construction 60.6% Sep 2026 1 mo past1 mo — 0
Serenity Mansions2718 · Al Hebiah Fourth · Tilal Al Ghaf Under construction 32.4% — — — 0

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.

Where the open projects are Projects not yet completed: 6, all pinned

2 projects2Alaya · 75–100% builtSerenity Mansions · 25–50% builtPlagette 32 · 50–75% builtAMARA · 50–75% built5 projects5AMARA · 50–75% builtMakani
25–50% built 50–75% built 75–100% built Approximate location (ringed)

Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.