DLD project no. 2259Completed808 units
Aura أورا Completed 13 October 2025 (DLD) · DLD end date Aug 2024 · DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.
Completed projects cannot be added to My units.
CompletionDLD readings of % built, beside the share of the planned period gone
% built
28 October 2026| Date | % built | Source |
|---|---|---|
| 10 October 2025 | 100% | DLD inspection |
| 3 July 2025 | 98.7% | DLD inspection |
| 1 May 2025 | 97.1% | DLD inspection |
| 10 March 2025 | 95.6% | DLD inspection |
| 25 November 2024 | 88.2% | DLD inspection |
| 28 October 2024 | 83.5% | DLD inspection |
| 10 July 2024 | 67.8% | DLD inspection |
| 12 May 2024 | 26% | DLD register, archived export |
| 6 March 2024 | 54.3% | DLD inspection |
| 21 September 2023 | 26.5% | DLD inspection |
| 28 March 2023 | 12.7% | DLD inspection |
| 23 November 2022 | 4.1% | DLD inspection |
| 5 August 2022 | 1% | DLD register, archived export |
| 4 July 2022 | 1.2% | DLD inspection |
| 14 February 2022 | 0.3% | DLD inspection |
Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗
Site timeline
± 6 monthsOur imagery reading holds no milestone for this project yet.
Our reading of historical satellite imagery
Registered period and actual build
Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.
Changes in the DLD register
No change to the end date, status or % built across the register exports we hold.
Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.
DLD registration
DLD services ↗Homes: villas 808.
Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: 808 Townhouses,(G+1+R) & (G+2+R).The project designed to have a concrete structure and block with internal and external finishes.
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
Dubai Statistics Center residential price index (villas), 2021-Q3 to 2026-Q2: +72.9%.
Prices are over villas and townhouses, the type most sales in this project are.
| Bedrooms | Launch price | Latest registered sales | Change |
|---|---|---|---|
| 3 BR | 1,162 (45) | 2,599 (16) | +123.7% |
| 4 BR | 1,067 (196) | 2,415 (15) | +126.3% |
| Bedrooms | Sales, 24 months | Latest median AED/sqft | Latest sales |
|---|---|---|---|
| 3 BR | 97 | 2,599 (16) | May 2026 – Nov 2026 |
| 4 BR | 135 | 2,415 (15) | May 2026 – Nov 2026 |
| 5 BR | 25 | 2,473 (10) | Nov 2025 – Nov 2026 |
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Median AED/sqft by quarter
2021-Q3 → 2026-Q4| Quarter | Registered sales | Median AED/sqft | DLD area Al Hebiah Fourth |
|---|---|---|---|
| 2021-Q3 | 239 (off-plan 239, ready 0) | 1,076 | 667 |
| 2021-Q4 | 524 (off-plan 524, ready 0) | 1,210 | 734 |
| 2022-Q1 | 55 (off-plan 55, ready 0) | 1,215 | 740 |
| 2022-Q2 | 23 (off-plan 23, ready 0) | 1,224 | 798 |
| 2022-Q3 | 20 (off-plan 20, ready 0) | 1,240 | 833 |
| 2022-Q4 | 24 (off-plan 24, ready 0) | 1,267 | 806 |
| 2023-Q1 | 60 (off-plan 60, ready 0) | 1,351 | 894 |
| 2023-Q2 | 58 (off-plan 58, ready 0) | 1,494 | 1,341 |
| 2023-Q3 | 29 (off-plan 29, ready 0) | 1,620 | 1,525 |
| 2023-Q4 | 40 (off-plan 40, ready 0) | 1,720 | 1,610 |
| 2024-Q1 | 36 (off-plan 36, ready 0) | 1,796 | 1,743 |
| 2024-Q2 | 34 (off-plan 34, ready 0) | 1,941 | 1,595 |
| 2024-Q3 | 21 (off-plan 21, ready 0) | 2,050 | 1,813 |
| 2024-Q4 | 32 (off-plan 32, ready 0) | 2,125 | 1,839 |
| 2025-Q1 | 36 (off-plan 27, ready 9) | 2,315 | 2,012 |
| 2025-Q2 | 36 (off-plan 18, ready 18) | 2,344 | 2,198 |
| 2025-Q3 | 29 (off-plan 9, ready 20) | 2,470 | 2,260 |
| 2025-Q4 | 56 (off-plan 0, ready 56) | 2,625 | 2,440 |
| 2026-Q1 | 33 (off-plan 0, ready 33) | 2,627 | 2,442 |
| 2026-Q2 | 23 (off-plan 0, ready 23) | 2,469 | 2,196 |
| 2026-Q3 | 15 (off-plan 0, ready 15) | 2,474 | 2,002 |
| 2026-Q4 | 6 (off-plan 0, ready 6) | 2,628 | 2,060 |
Median AED/sqft of registered sales per quarter (villas and townhouses). Source: DLD. Grey dashed line: DLD area Al Hebiah Fourth, median AED/sqft of ready sales of villas and townhouses by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.
Registered sales per quarter
| Quarter | Registered sales | Median AED/sqft | DLD area Al Hebiah Fourth |
|---|---|---|---|
| 2021-Q3 | 239 (off-plan 239, ready 0) | 1,076 | 667 |
| 2021-Q4 | 524 (off-plan 524, ready 0) | 1,210 | 734 |
| 2022-Q1 | 55 (off-plan 55, ready 0) | 1,215 | 740 |
| 2022-Q2 | 23 (off-plan 23, ready 0) | 1,224 | 798 |
| 2022-Q3 | 20 (off-plan 20, ready 0) | 1,240 | 833 |
| 2022-Q4 | 24 (off-plan 24, ready 0) | 1,267 | 806 |
| 2023-Q1 | 60 (off-plan 60, ready 0) | 1,351 | 894 |
| 2023-Q2 | 58 (off-plan 58, ready 0) | 1,494 | 1,341 |
| 2023-Q3 | 29 (off-plan 29, ready 0) | 1,620 | 1,525 |
| 2023-Q4 | 40 (off-plan 40, ready 0) | 1,720 | 1,610 |
| 2024-Q1 | 36 (off-plan 36, ready 0) | 1,796 | 1,743 |
| 2024-Q2 | 34 (off-plan 34, ready 0) | 1,941 | 1,595 |
| 2024-Q3 | 21 (off-plan 21, ready 0) | 2,050 | 1,813 |
| 2024-Q4 | 32 (off-plan 32, ready 0) | 2,125 | 1,839 |
| 2025-Q1 | 36 (off-plan 27, ready 9) | 2,315 | 2,012 |
| 2025-Q2 | 36 (off-plan 18, ready 18) | 2,344 | 2,198 |
| 2025-Q3 | 29 (off-plan 9, ready 20) | 2,470 | 2,260 |
| 2025-Q4 | 56 (off-plan 0, ready 56) | 2,625 | 2,440 |
| 2026-Q1 | 33 (off-plan 0, ready 33) | 2,627 | 2,442 |
| 2026-Q2 | 23 (off-plan 0, ready 23) | 2,469 | 2,196 |
| 2026-Q3 | 15 (off-plan 0, ready 15) | 2,474 | 2,002 |
| 2026-Q4 | 6 (off-plan 0, ready 6) | 2,628 | 2,060 |
Registered sales per quarter, off-plan and ready units. Source: DLD.
What launch buyers got
The launch price against the registered resales after completion, same home types on both sides.
Over the same span, ready homes in DLD area Al Hebiah Fourth changed +64.3% (same home types).
Launch: the 90 days from the first off-plan sale (2020 onward). Resales: ready sales in the 12 months after the DLD completion date, or 24 when 12 hold fewer than 5. A price change is not a return: it leaves out fees, service charges, rent and the payment plan.
Rents and gross yield
New Ejari rent contracts for villas and townhouses in this project, 12 months to 5 November 2026, against the 12 months before. Gross yield: the median annual rent over the median registered ready sale price of the same bedroom count in this project over the same 12 months.
| Bedrooms | Median annual rent | New contracts | Change on a year earlier | Gross yield |
|---|---|---|---|---|
| 3 BR | AED 220,000 | 149 | -6.4% | 5.2% |
| 4 BR | AED 300,000 | 195 | -6.2% | 4.8% |
| 5 BR | AED 335,000 | 32 | +4.7% | 5.4% |
Gross yield is before service charges, other costs and empty months.
New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.
Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.
Mortgage registrations
Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.
| Quarter | Mortgage registrations |
|---|---|
| 2024-Q1 | 0 |
| 2024-Q2 | 0 |
| 2024-Q3 | 0 |
| 2024-Q4 | 0 |
| 2025-Q1 | 13 · registered amount AED 45.2M |
| 2025-Q2 | 41 · registered amount AED 159.3M |
| 2025-Q3 | 57 · registered amount AED 173.7M |
| 2025-Q4 | 122 · registered amount AED 337.2M |
| 2026-Q1 | 62 · registered amount AED 191M |
| 2026-Q2 | 51 · registered amount AED 148.6M |
| 2026-Q3 | 22 · registered amount AED 78M |
| 2026-Q4 | 13 · registered amount AED 40M |
Mortgage registrations on homes per quarter. Source: DLD.
Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 148; registered amount AED 457.6M.
Since the first registration in 2025-Q1: 381 in all.
Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
Registered sales
The newest sales DLD has registered in this project, as DLD publishes them.
| Date | Market | Type | Size (sqft) | Price (AED) | AED/sqft |
|---|---|---|---|---|---|
| 3 November 2026 | ready | Villa · 3 BR | 1,545 | 4,175,000 | 2,702 |
| 27 October 2026 | ready | Villa · 4 BR | 2,373 | 6,850,000 | 2,887 |
| 14 October 2026 | ready | Villa · 3 BR | 1,566 | 4,150,000 | 2,650 |
| 7 October 2026 | ready | Villa · 4 BR | 2,508 | 5,575,000 | 2,223 |
| 5 October 2026 | ready | Villa · 4 BR | 2,692 | 6,500,000 | 2,415 |
| 2 October 2026 | ready | Villa · 3 BR | 1,522 | 4,000,000 | 2,628 |
| 15 September 2026 | ready | Villa · 4 BR | 2,946 | 7,100,000 | 2,410 |
| 7 September 2026 | ready | Villa · 3 BR | 2,547 | 6,300,000 | 2,473 |
| 4 September 2026 | ready | Villa · 3 BR | 1,512 | 3,900,000 | 2,579 |
| 1 September 2026 | ready | Villa · 4 BR | 2,373 | 6,400,000 | 2,697 |
Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
LocationAl Hebiah Fourth · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
School ratings: KHDA’s school directory ↗ · Report a wrong location
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 25, with 4,118 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2017 | 1 | 172 |
| 2024 | 1 | 554 |
| 2025 | 2 | 8 |
| 2026 | 7 | 1,546 |
| 2027 | 3 | 897 |
| 2028 | 3 | 605 |
| 2029 | 1 | 0 |
| 2030 | 1 | 336 |
| No end date | 6 | 0 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Al Hebiah Fourth: 35
Open projects in the same DLD area, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Binghatti Haven | 76.1% | Mar 2026 | 1,489 | 485 |
| Azizi Grand | 82.1% | Feb 2025 | 1,351 | 290 |
| ASPIRZ By Danube | 5.1% | Dec 2028 | 2,216 | 267 |
| Verde By Vision | 12% | Sep 2027 | 1,388 | 236 |
| The Community - Sports Arena | 22.4% | Oct 2027 | 1,320 | 217 |
| Hadley Heights 2 | 0% | Oct 2027 | 1,306 | 193 |
| Sportz By Danube | 80.2% | Mar 2026 | 1,594 | 146 |
| Mag 777 | 67.4% | Jan 2026 | — | 142 |
| Urban Park Residences | 67.6% | Apr 2026 | 1,519 | 121 |
| Antalya By Karma | 0.1% | Sep 2028 | 1,491 | 108 |
| Golf Residences By Prestige One | 35.7% | Feb 2028 | 1,258 | 104 |
| Vega | 20.3% | May 2027 | 1,519 | 103 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Majid Al Futtaim Tilal Al Ghaf Phase A L.L.C · DLD developer no. 1228
Completed a month or more after their DLD end date: 2 of 3 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
Majid Al Futtaim Tilal Al Ghaf Phase A L.L.C is one of 8 DLD-registered developers we list together as Majid Al Futtaim. See the group
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Other projects in Tilal Al Ghaf
DLD lists 8 projects in the master project Tilal Al Ghaf.
Questions about Aura
When was Aura completed?
Aura is recorded as completed on 13 October 2025 (DLD register of 1 November 2026).
Who is the developer of Aura?
Majid Al Futtaim Tilal Al Ghaf Phase A L.L.C, as registered with DLD.
What is the DLD project number of Aura?
2259.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error